1.1A bill for an act
1.2relating to mining; improving coordination, effectiveness, transparency, and
1.3accountability of environmental review and permitting process for metallic mineral
1.4mining projects; proposing coding for new law in Minnesota Statutes, chapter 93.
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.6Section 1. new text begin [93.70] PURPOSE. new text end
1.7 new text begin The purpose of sections 93.70 to 93.711 is to improve the coordination, effectiveness, new text end
1.8 new text begin transparency, and accountability of the environmental review and permitting process for new text end
1.9 new text begin metallic mineral mining projects. new text end
1.10Sec. 2. new text begin [93.705] DEFINITIONS. new text end
1.11 new text begin Subdivision 1. Applicability. For purposes of sections 93.70 to 93.711, the terms defined new text end
1.12 new text begin in this section have the meanings given. new text end
1.13 new text begin Subd. 2. Commissioner. "Commissioner" means the commissioner of natural resources. new text end
1.14 new text begin Subd. 3. Covered mining project. "Covered mining project" means a proposed metallic new text end
1.15 new text begin mineral mining project or a modification to an existing metallic mining project for which new text end
1.16 new text begin an environmental assessment worksheet or an environmental impact statement must be or new text end
1.17 new text begin is being prepared according to chapter 116D, unless the project proposer requests that its new text end
1.18 new text begin project be excluded from the requirements of sections 93.70 to 93.711. new text end
1.19 new text begin Subd. 4. Dashboard. "Dashboard" means the online tool required under section 93.706, new text end
1.20 new text begin subdivision 1. new text end
2.1 new text begin Subd. 5. Participating agency. "Participating agency" means a state agency that has new text end
2.2 new text begin regulatory authority over a covered mining project. Participating agency does not include new text end
2.3 new text begin a state agency that informs the commissioner in writing that it does not intend to exercise new text end
2.4 new text begin authority with respect to or submit comments in connection with a covered mining project. new text end
2.5 new text begin Subd. 6. Submission date. "Submission date" means the date on which a project proposer new text end
2.6 new text begin submits the completed data portion of an environmental assessment worksheet to the new text end
2.7 new text begin responsible governmental unit for environmental review under chapter 116D. new text end
2.8Sec. 3. new text begin [93.706] ENVIRONMENTAL AND PERMITTING REVIEW DASHBOARD. new text end
2.9 new text begin Subdivision 1. Dashboard required. The commissioner must create an environmental new text end
2.10 new text begin review and permitting dashboard as an online tool for state and federal agencies, project new text end
2.11 new text begin proposers, and interested members of the public to list and track environmental review and new text end
2.12 new text begin permitting documents for covered mining projects. new text end
2.13 new text begin Subd. 2. Adding project to dashboard; summary of project. The commissioner must new text end
2.14 new text begin add a project to the dashboard within 15 days of the environmental assessment worksheet new text end
2.15 new text begin submission date. Not later than 30 days after a project is added to the dashboard, the new text end
2.16 new text begin commissioner must add to the dashboard a summary that includes: new text end
2.17 new text begin (1) a statement of the purposes and objectives of the project; new text end
2.18 new text begin (2) a concise description of the project, including: new text end
2.19 new text begin (i) the general location of the project; and new text end
2.20 new text begin (ii) a summary of geospatial information, if available, illustrating the project area and new text end
2.21 new text begin the locations, if any, of environmental, cultural, and historic resources; new text end
2.22 new text begin (3) a statement of any anticipated environmental reviews and local, state, and federal new text end
2.23 new text begin permits to be required to complete the project; and new text end
2.24 new text begin (4) a statement of any public hearings and opportunities to comment on environmental new text end
2.25 new text begin review and permits for the project. new text end
2.26 new text begin Subd. 3. Posting additional information. To the extent allowed by applicable law, the new text end
2.27 new text begin commissioner must add and maintain the following project information to the dashboard new text end
2.28 new text begin within 15 days of receiving it from a project proposer or from a participating agency: new text end
2.29 new text begin (1) a hyperlink to a website that contains the completed data portions of the environmental new text end
2.30 new text begin assessment worksheet, permit applications, and supporting documents for any required new text end
2.31 new text begin environmental review or permit or a notice explaining how the public may obtain access to new text end
2.32 new text begin these documents; new text end
3.1 new text begin (2) the environmental review and permitting deadlines for the project; new text end
3.2 new text begin (3) the compliance status of each participating agency with the environmental review new text end
3.3 new text begin and permitting deadlines, including any information received by the commissioner under new text end
3.4 new text begin section 93.707, subdivision 5; new text end
3.5 new text begin (4) any modification to the environmental review and permitting deadlines, along with new text end
3.6 new text begin an explanation of the modification; new text end
3.7 new text begin (5) any memorandum of understanding for the project; new text end
3.8 new text begin (6) a description of any action taken or decision made by a participating agency that new text end
3.9 new text begin materially affects the status of the environmental review or permit for the project; and new text end
3.10 new text begin (7) a description of the status of any litigation to which a state agency is a party and that new text end
3.11 new text begin is directly related to the project, including, if practicable, any judicial document made new text end
3.12 new text begin available on an electronic docket maintained by a federal, state, or local court. new text end
3.13 new text begin Subd. 4. Participating agencies; duties. (a) Within five days of a participating agency new text end
3.14 new text begin receiving the completed data portion of the environmental assessment worksheet for a new text end
3.15 new text begin covered mining project for which the participating agency is the responsible governmental new text end
3.16 new text begin unit under chapter 116D, the participating agency must notify the commissioner of the new text end
3.17 new text begin submission date and, no later than 20 days after the submission date, provide to the new text end
3.18 new text begin commissioner the information described in subdivision 2. new text end
3.19 new text begin (b) Each participating agency that possesses or receives any of the information described new text end
3.20 new text begin in subdivision 3 must immediately submit the information to the commissioner for inclusion new text end
3.21 new text begin in the dashboard under subdivision 3. new text end
3.22Sec. 4. new text begin [93.707] COORDINATED PROJECT PLAN. new text end
3.23 new text begin Subdivision 1. Coordinated project plan required. Within 60 days of the date by which new text end
3.24 new text begin a project is required to be added to the dashboard under section 93.706, subdivision 2, the new text end
3.25 new text begin commissioner, in coordination with the other participating agencies and the project proposer, new text end
3.26 new text begin must establish a coordinated project plan for coordinating public and agency participation new text end
3.27 new text begin in and completing any required environmental review and permits for the project. A new text end
3.28 new text begin coordinated project plan may be incorporated into a memorandum of understanding with new text end
3.29 new text begin other state and federal agencies and Tribes. new text end
3.30 new text begin Subd. 2. Updating; required contents. The commissioner must update a coordinated new text end
3.31 new text begin project plan quarterly. A plan must include: new text end
4.1 new text begin (1) a list of all entities with environmental review or permitting responsibility for the new text end
4.2 new text begin project, including an explanation of each entity's specific roles and responsibilities; new text end
4.3 new text begin (2) plans and a schedule for public and Tribal outreach and coordination, to the extent new text end
4.4 new text begin required by applicable law; and new text end
4.5 new text begin (3) a comprehensive schedule of deadlines by which all environmental reviews, permits, new text end
4.6 new text begin and approvals, including those at the federal level to the extent practicable, must be new text end
4.7 new text begin completed. The deadlines established under this clause must include intermediate and final new text end
4.8 new text begin completion deadlines for actions by each participating agency and, except as provided in new text end
4.9 new text begin subdivision 3, must be consistent with the following: new text end
4.10 new text begin (i) when an environmental assessment worksheet is prepared for a project for which an new text end
4.11 new text begin environmental impact statement is not required, the decision on the need for an environmental new text end
4.12 new text begin impact statement must be made no later than 18 months after the environmental assessment new text end
4.13 new text begin worksheet submission date; and new text end
4.14 new text begin (ii) when an environmental impact statement is prepared for a project, the decision on new text end
4.15 new text begin the adequacy of the final environmental impact statement must be made no later than three new text end
4.16 new text begin years after the environmental assessment worksheet submission date. new text end
4.17 new text begin Subd. 3. Alternative deadlines. If the commissioner includes deadlines that are new text end
4.18 new text begin inconsistent with subdivision 2, clause (3), in a coordinated project plan, within five days new text end
4.19 new text begin the commissioner must report to the chairs and ranking minority members of the legislative new text end
4.20 new text begin committees and divisions with jurisdiction over mining to explain the reason for the decision, new text end
4.21 new text begin including an explanation of why the deadlines under subdivision 2, clause (3), are inadequate. new text end
4.22 new text begin The anticipated time required to obtain a federal permit or decision may not serve as the new text end
4.23 new text begin basis for a decision to deviate from the deadlines under subdivision 2, clause (3). new text end
4.24 new text begin Subd. 4. Modifying deadlines. (a) The commissioner may modify a deadline established new text end
4.25 new text begin in a coordinated project plan only if: new text end
4.26 new text begin (1) the commissioner or the applicable participating agency provides the project proposer new text end
4.27 new text begin with a written justification for the modification; and new text end
4.28 new text begin (2) the commissioner and affected participating agencies, after consultation with the new text end
4.29 new text begin project proposer, subsequently agree to a different deadline. new text end
4.30 new text begin (b) If the combined modifications to one or more deadlines established in a coordinated new text end
4.31 new text begin project plan extend the initially anticipated project completion date by more than 20 percent: new text end
4.32 new text begin (1) within five days of the most recent modification, the commissioner must report to new text end
4.33 new text begin the chairs and ranking minority members of the legislative committees and divisions with new text end
5.1 new text begin jurisdiction over mining to explain the reason the modifications are necessary. For purposes new text end
5.2 new text begin of calculating the percentage of time that modifications have extended the anticipated project new text end
5.3 new text begin completion date, modifications made necessary by reasons completely outside the control new text end
5.4 new text begin of state agencies must not be considered; and new text end
5.5 new text begin (2) the commissioner must annually submit to the committees and divisions under clause new text end
5.6 new text begin (1) a report on progress toward final completion of the project until the earlier of the new text end
5.7 new text begin completion of final environmental review and permitting actions by state agencies or the new text end
5.8 new text begin withdrawal of the proposal by its proposer. new text end
5.9 new text begin Subd. 5. Participating agencies; duties. (a) Each participating agency must meet the new text end
5.10 new text begin deadlines established in the applicable coordinated project plan. new text end
5.11 new text begin (b) If a participating agency fails to meet a deadline established in a coordinated project new text end
5.12 new text begin plan or anticipates failing to meet a deadline, the agency must immediately: new text end
5.13 new text begin (1) notify the commissioner of the failure or anticipated failure; new text end
5.14 new text begin (2) explain the reason for the failure or anticipated failure; and new text end
5.15 new text begin (3) propose a date for a modified deadline. new text end
5.16 new text begin (c) After the commissioner receives the information under paragraph (b), the new text end
5.17 new text begin commissioner must modify the deadline according to subdivision 4. Until the modified new text end
5.18 new text begin deadline is met, the participating agency must submit monthly progress reports to the new text end
5.19 new text begin commissioner on the agency's progress in meeting the modified deadline. new text end
5.20Sec. 5. new text begin [93.708] COORDINATION. new text end
5.21 new text begin Subdivision 1. Synchronization required. To the extent practicable under applicable new text end
5.22 new text begin law, the commissioner and participating agencies must synchronize state environmental new text end
5.23 new text begin review and permitting processes for a covered mining project with any federal, local, or new text end
5.24 new text begin Tribal agency responsible for conducting any review or authorization of the project to ensure new text end
5.25 new text begin timely and efficient completion of environmental reviews and authorizations. To the extent new text end
5.26 new text begin practicable, any synchronization plan must be included in a memorandum of understanding. new text end
5.27 new text begin Subd. 2. Facilitating early communication. To the extent practicable, the commissioner new text end
5.28 new text begin must establish and provide an expeditious process for project proposers to confer with new text end
5.29 new text begin participating agencies, federal agencies, Tribal agencies, and local agencies and to obtain new text end
5.30 new text begin from those agencies, within 60 days of a request, information about: new text end
5.31 new text begin (1) the availability of information and tools, including pre-application toolkits, to facilitate new text end
5.32 new text begin early planning efforts; new text end
6.1 new text begin (2) key issues of concern to each agency and to the public; and new text end
6.2 new text begin (3) issues that must be addressed before an environmental review, authorization, or new text end
6.3 new text begin permit can be completed. new text end
6.4 new text begin Subd. 3. Identifying potential problems. Each participating agency must: new text end
6.5 new text begin (1) identify, as early as practicable, any issues of concern regarding the potential new text end
6.6 new text begin environmental impacts of a covered mining project, including any issues that could new text end
6.7 new text begin substantially delay or prevent an agency from completing any environmental review or new text end
6.8 new text begin permitting process required for the project; and new text end
6.9 new text begin (2) communicate those issues to the commissioner and to the project proposer. new text end
6.10Sec. 6. new text begin [93.709] BEST PRACTICES. new text end
6.11 new text begin By July 1, 2026, and every two years thereafter, the commissioner must issue new text end
6.12 new text begin recommended best practices for environmental review and permitting of covered mining new text end
6.13 new text begin projects designed to: new text end
6.14 new text begin (1) enhance early stakeholder engagement; new text end
6.15 new text begin (2) ensure timely decisions regarding environmental reviews and permits, including by new text end
6.16 new text begin developing performance metrics; new text end
6.17 new text begin (3) improve coordination between state and nonstate governmental entities, including new text end
6.18 new text begin by developing common data standards and terminology across agencies; new text end
6.19 new text begin (4) increase transparency; and new text end
6.20 new text begin (5) reduce information-collection requirements and other administrative burdens on new text end
6.21 new text begin agencies, project proposers, and other interested parties. new text end
6.22Sec. 7. new text begin [93.71] RELATION TO OTHER LAW. new text end
6.23 new text begin (a) Nothing in sections 93.70 to 93.711 is to be construed to require an act that conflicts new text end
6.24 new text begin with applicable federal law. new text end
6.25 new text begin (b) Nothing in sections 90.70 to 93.711 in any way affects the specific statutory new text end
6.26 new text begin obligations of a state agency to comply with criteria or standards of environmental quality. new text end
6.27Sec. 8. new text begin [93.711] REPORT. new text end
6.28 new text begin By April 15 each year, the commissioner must submit a report to the chairs and ranking new text end
6.29 new text begin minority members of the legislative committees and divisions with jurisdiction over mining. new text end
7.1 new text begin The report must describe progress during the previous fiscal year in making new text end
7.2 new text begin environmental-review and permitting-process improvements under sections 93.70 to 93.709 new text end
7.3 new text begin and assess the performance of each participating agency in implementing the improvements. new text end
7.4Sec. 9. new text begin ADDING OTHER MINING PROJECTS TO DASHBOARD. new text end
7.5 new text begin For any metallic mineral mining project for which an environmental assessment worksheet new text end
7.6 new text begin or an environmental impact statement was prepared according to Minnesota Statutes, chapter new text end
7.7 new text begin 116D, before the effective date of sections 1 to 8, the commissioner of natural resources new text end
7.8 new text begin must add the information described in Minnesota Statutes, section 93.706, subdivision 2, new text end
7.9 new text begin to the dashboard required by Minnesota Statutes, section 93.706, subdivision 1. new text end

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.