1.1A bill for an act
1.2relating to energy; requiring the inclusion of nuclear power as an optional resource
1.3in a utility's integrated resource plan; requiring the state to apply for federal funding
1.4related to nuclear-powered electric generating plants; amending Minnesota Statutes
1.52024, section 216B.2422, subdivision 2; proposing coding for new law in Minnesota
1.6Statutes, chapter 216C.
1.7BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.8Section 1. Minnesota Statutes 2024, section 216B.2422, subdivision 2, is amended to read:
1.9Subd. 2. Resource plan filing and approval. (a) A utility shall file a resource plan with
1.10the commission periodically in accordance with rules adopted by the commission. The
1.11commission shall approve, reject, or modify the plan of a public utility, as defined in section
1.12216B.02, subdivision 4, consistent with the public interest.
1.13(b) In the resource plan proceedings of all other utilities, the commission's order shall
1.14be advisory and the order's findings and conclusions shall constitute prima facie evidence
1.15which may be rebutted by substantial evidence in all other proceedings. With respect to
1.16utilities other than those defined in section 216B.02, subdivision 4, the commission shall
1.17consider the filing requirements and decisions in any comparable proceedings in another
1.18jurisdiction.
1.19(c) As a part of its resource plan filing, a utility shall include the least cost plan for
1.20meeting 50 and 75 percent of all energy needs from both new and refurbished generating
1.21facilities through a combination of conservation and renewable energy resources.
1.22 new text begin (d) Notwithstanding section 216B.243, subdivision 3b, paragraph (a), a utility that new text end
1.23 new text begin provides electric service may include the deployment of nuclear-powered electric generating new text end
2.1 new text begin plants in the utility's resource plan filing. If a nuclear-powered electric generating plant is new text end
2.2 new text begin not selected as a preferred resource, the utility must present the reasons why the utility made new text end
2.3 new text begin that determination. new text end
2.4 new text begin EFFECTIVE DATE. This section is effective the day following final enactment and new text end
2.5 new text begin applies to integrated resource plans filed after September 1, 2026. new text end
2.6Sec. 2. new text begin [216C.395] APPLICATION FOR FEDERAL FUNDING; NUCLEAR POWER; new text end
2.7 new text begin REPORTS. new text end
2.8 new text begin (a) The department must monitor federal funding opportunities related to nuclear-powered new text end
2.9 new text begin electric generating plants and must apply for all projects for which Minnesota is eligible. new text end
2.10 new text begin (b) No later than February 1, 2027, and by February 1 each year thereafter, the department new text end
2.11 new text begin must submit a written report to the chairs and ranking minority members of the legislative new text end
2.12 new text begin committees with jurisdiction over energy finance and policy documenting each application new text end
2.13 new text begin filed under paragraph (a) and the results of each application. For all projects for which the new text end
2.14 new text begin department did not submit an application, the department must include the reason why the new text end
2.15 new text begin department determined that Minnesota is an ineligible applicant. new text end
2.16 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.