1.1A bill for an act
1.2relating to data centers; modifying the criteria for preapplication evaluations of
1.3water appropriations for certain data centers; exempting certain data centers'
1.4electricity sales in calculating a utility's solar energy standard; exempting certain
1.5data centers from paying a fee; exempting certain data centers from paying sales
1.6tax on electricity purchases; amending Minnesota Statutes 2025 Supplement,
1.7sections 103G.265, subdivision 5; 216B.02, subdivision 12; 216B.1623; 216B.1691,
1.8subdivision 2f; 216B.72; 297A.68, subdivision 42.
1.9BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.10Section 1. Minnesota Statutes 2025 Supplement, section 103G.265, subdivision 5, is
1.11amended to read:
1.12Subd. 5. Preapplication evaluation of certain water appropriation projects. (a) This
1.13subdivision applies to a data center, as defined in section 216B.02, subdivision 11, whose
1.14proposed new text begin net increase in new text end consumptive use exceeds 100,000,000 gallons per year and which
1.15requires a permit amendment or a new individual permit.
1.16(b) In response to a contact from a data center regarding a project that is likely to be
1.17subject to this subdivision, the department may request preapplication information from the
1.18data center that is helpful in assisting the department to assess the factors affecting the ability
1.19of a water source to meet a project's water use needs at a proposed location, including:
1.20(1) a project description;
1.21(2) the project's estimated water use rates and volumes for the maximum day, maximum
1.22month, and average year;
1.23(3) the anticipated source of water; and
1.24(4) water quality or temperature requirements.
2.1(c) The department may request any additional information necessary from the data
2.2center to assist it to assess the ability of a water source to meet a project's water use needs.
2.3(d) The commissioner shall evaluate the information supplied under this subdivision
2.4and shall respond in writing, which may be electronically transmitted, describing potential
2.5water availability constraints at each proposed project site.
2.6(e) In determining the impact of a potential project on water quality and quantity, the
2.7commissioner may consult with the commissioners of health, agriculture, and the Pollution
2.8Control Agency, and other state agencies.
2.9(f) Any communication made or information exchanged under this subdivision between
2.10a data center and a government agency, or between government agencies, is nonpublic data,
2.11as defined in section 13.02, subdivision 9.
2.12(g) None of the discussions, filings, or evaluations made under this subdivision preclude
2.13or supplant environment review, preliminary well-construction approval, appropriation
2.14permit review, or any other requirements under federal, state, or local law.
2.15 new text begin (h) For the purposes of this subdivision, "net increase in consumptive use" means the new text end
2.16 new text begin estimated net increase in annual water consumption by a data center after subtracting new text end
2.17 new text begin documented reductions in consumption from the same water source by other entities that new text end
2.18 new text begin occurred within the previous ... years or that are scheduled to occur within ... years of the new text end
2.19 new text begin date the data center initiated operations. new text end
2.20 new text begin (i) This section does not apply to a qualified large-scale data center, as defined in section new text end
2.21 new text begin 297A.68, subdivision 42, that: new text end
2.22 new text begin (1) has filed an application on or before January 1, 2025, with a county, town, or new text end
2.23 new text begin municipality for a permit or approval that is necessary to authorize construction; or new text end
2.24 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
2.25 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
2.26Sec. 2. Minnesota Statutes 2025 Supplement, section 216B.02, subdivision 12, is amended
2.27to read:
2.28Subd. 12. Qualified large-scale data center. "Qualified large-scale data center" has the
2.29meaning given in section 297A.68, subdivision 42 deleted text begin , paragraph (e) deleted text end .
2.30 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.1Sec. 3. Minnesota Statutes 2025 Supplement, section 216B.1623, is amended to read:
3.2216B.1623 CLEAN ENERGY AND CAPACITY TARIFF.
3.3 new text begin Subdivision 1. Tariff offer. new text end The commission shall require each public utility to offer a
3.4clean energy and capacity tariff for commercial and industrial customers. The clean energy
3.5and capacity tariff shall require a special contract between the utility and one or more
3.6customers that shall:
3.7(1) be optional for participating customers;
3.8(2) permit participating customers to elect to serve some or all of their energy or capacity
3.9usage from new clean energy or capacity resources as long as reliability is maintained;
3.10(3) require the participating customers to pay all proportional costs associated with the
3.11addition of the new clean energy or capacity resources, including any utility costs caused
3.12by the addition of the new clean energy or capacity resources to the grid;
3.13(4) develop an appropriate energy and capacity credit;
3.14(5) prohibit cost shifting from the participating customers to other utility customers or
3.15vice versa; and
3.16(6) allow a utility with an applicable tariff on file to demonstrate their existing tariff's
3.17compliance with this section.
3.18 new text begin Subd. 2. Exemptions. This subdivision does not apply to a qualified large-scale data new text end
3.19 new text begin center that: new text end
3.20 new text begin (1) has filed an application on or before January 1, 2025, with a county, town, or new text end
3.21 new text begin municipality for a permit or approval that is necessary to authorize construction; or new text end
3.22 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
3.23 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.24Sec. 4. Minnesota Statutes 2025 Supplement, section 216B.1691, subdivision 2f, is amended
3.25to read:
3.26Subd. 2f. Solar energy standard. (a) In addition to the requirements of subdivisions 2a
3.27and 2g, each public utility shall generate or procure sufficient electricity generated by solar
3.28energy to serve its retail electricity customers in Minnesota so that by the end of 2020, at
3.29least 1.5 percent of the utility's total retail electric sales to retail customers in Minnesota is
3.30generated by solar energy.
4.1(b) For a public utility with more than 200,000 retail electric customers, at least ten
4.2percent of the 1.5 percent goal must be met by solar energy generated by or procured from
4.3solar photovoltaic devices with a nameplate capacity of 40 kilowatts or less.
4.4(c) A public utility with between 50,000 and 200,000 retail electric customers:
4.5(1) must meet at least ten percent of the 1.5 percent goal with solar energy generated by
4.6or procured from solar photovoltaic devices with a nameplate capacity of 40 kilowatts or
4.7less; and
4.8(2) may apply toward the ten percent goal in clause (1) individual customer subscriptions
4.9of 40 kilowatts or less to a community solar garden program operated by the public utility
4.10that has been approved by the commission.
4.11(d) The solar energy standard established in this subdivision is subject to all the provisions
4.12of this section governing a utility's standard obligation under subdivision 2a.
4.13(e) It is an energy goal of the state of Minnesota that, by 2030, ten percent of the retail
4.14electric sales in Minnesota be generated by solar energy.
4.15(f) For the purposes of calculating the total retail electric sales of a public utility deleted text begin serving deleted text end
4.16 deleted text begin fewer than 200,000 retail electric customers deleted text end under this subdivision, there shall be excluded
4.17retail electric sales to customers that are:
4.18 new text begin (1) served by a public utility with fewer than 200,000 retail electric customers and are: new text end
4.19 deleted text begin (1) deleted text end new text begin (i) new text end an iron mining extraction and processing facility, including a scram mining facility
4.20as defined in Minnesota Rules, part 6130.0100, subpart 16;
4.21 deleted text begin (2) deleted text end new text begin (ii) new text end a qualified large-scale data center; or
4.22 deleted text begin (3) deleted text end new text begin (iii) new text end a paper mill, wood products manufacturer, sawmill, or oriented strand board
4.23manufacturer deleted text begin . deleted text end new text begin ; or new text end
4.24 new text begin (2) a qualified large-scale data center that: new text end
4.25 new text begin (i) has filed an application on or before January 1, 2025, with a county, town, or new text end
4.26 new text begin municipality for a permit or approval that is necessary to authorize construction; or new text end
4.27 new text begin (ii) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
4.28 deleted text begin Those deleted text end Customers new text begin identified in clause (1) or (2) new text end may not have included in the rates charged
4.29to them by the public utility deleted text begin serving fewer than 200,000 retail electric customers deleted text end any costs
4.30of satisfying the solar standard specified by this subdivision.
5.1(g) A public utility may not use energy used to satisfy the solar energy standard under
5.2this subdivision to satisfy its standard obligation under subdivision 2a. A public utility may
5.3not use energy used to satisfy the standard obligation under subdivision 2a to satisfy the
5.4solar standard under this subdivision.
5.5(h) Notwithstanding any law to the contrary, a solar renewable energy credit associated
5.6with a solar photovoltaic device installed and generating electricity in Minnesota after
5.7August 1, 2013, but before 2020 may be used to meet the solar energy standard established
5.8under this subdivision.
5.9 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
5.10Sec. 5. Minnesota Statutes 2025 Supplement, section 216B.72, is amended to read:
5.11216B.72 QUALIFIED LARGE-SCALE DATA CENTER FEE.
5.12(a) new text begin Except as provided in paragraph (d), new text end the commissioner must collect an annual fee
5.13from deleted text begin the deleted text end new text begin a new text end qualified large-scale data center, on a schedule prescribed by the commissioner
5.14and deposited in the energy and conservation account established in section 216B.241,
5.15subdivision 2a.
5.16(b) The fee is based on deleted text begin the deleted text end new text begin a new text end qualified large-scale data center's peak demand the utility
5.17arranges to serve, reflecting the qualified large-scale data center's peak demand forecast
5.18provided to the utility, expressed in megawatts (MW), as follows:
5.19Peak Demand Fee
5.20(1) 100 to 250 MW $2,000,000
5.21(2) above 250 MW but below 500 MW $3,000,000
5.22(3) 500 MW but below 750 MW $4,000,000
5.23(4) 750 MW or greater $5,000,000
5.24(c) The fee data collected under this section must be treated as nonpublic data, as defined
5.25under section 13.02, subdivision 9.
5.26 new text begin (d) This section does not apply to a qualified large-scale data center that: new text end
5.27 new text begin (1) has filed an application on or before January 1, 2025, with a county, town, or new text end
5.28 new text begin municipality for a permit or approval that is necessary to authorize construction; or new text end
5.29 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
5.30 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
6.1Sec. 6. Minnesota Statutes 2025 Supplement, section 297A.68, subdivision 42, is amended
6.2to read:
6.3Subd. 42. Data centers. (a) Purchases of enterprise information technology equipment
6.4and computer software for use in a qualified data center, a qualified refurbished data center,
6.5or a qualified large-scale data center are exempt, except that computer software maintenance
6.6agreements are exempt for purchases made after June 30, 2013. The tax on purchases exempt
6.7under this paragraph must be imposed and collected as if the rate under section 297A.62,
6.8subdivision 1, applied, and then refunded after June 30, 2013, in the manner provided in
6.9section 297A.75. This exemption includes enterprise information technology equipment
6.10and computer software purchased to replace or upgrade enterprise information technology
6.11equipment and computer software in a qualified data center, a qualified refurbished data
6.12center, or a qualified large-scale data center.
6.13 new text begin (b) A purchase of electricity used or consumed to operate a qualified large-scale data new text end
6.14 new text begin center located in an eligible community, as defined in section 116J.55, subdivision 1, is new text end
6.15 new text begin exempt. new text end
6.16 deleted text begin (b) deleted text end new text begin (c) new text end For purposes of this subdivision, "qualified data center" means a facility in
6.17Minnesota:
6.18(1) that is comprised of one or more buildings that consist in the aggregate of at least
6.1925,000 square feet, and that are located on a single parcel or on contiguous parcels, where
6.20the total cost of construction or refurbishment, investment in enterprise information
6.21technology equipment, and computer software is at least $30,000,000 within a 48-month
6.22period. The 48-month period begins no sooner than July 1, 2012, except that costs for
6.23computer software maintenance agreements purchased before July 1, 2013, are not included
6.24in determining if the $30,000,000 threshold has been met;
6.25(2) that is constructed or substantially refurbished after June 30, 2012, where
6.26"substantially refurbished" means that at least 25,000 square feet have been rebuilt or
6.27modified, including:
6.28(i) installation of enterprise information technology equipment; environmental control,
6.29computer software, and energy efficiency improvements; and
6.30(ii) building improvements; and
6.31(3) that is used to house enterprise information technology equipment, where the facility
6.32has the following characteristics:
6.33(i) uninterruptible power supplies, generator backup power, or both;
7.1(ii) sophisticated fire suppression and prevention systems; and
7.2(iii) enhanced security. A facility will be considered to have enhanced security if it has
7.3restricted access to the facility to selected personnel; permanent security guards; video
7.4camera surveillance; an electronic system requiring pass codes, keycards, or biometric scans,
7.5such as hand scans and retinal or fingerprint recognition; or similar security features.
7.6In determining whether the facility has the required square footage, the square footage
7.7of the following spaces shall be included if the spaces support the operation of enterprise
7.8information technology equipment: office space, meeting space, and mechanical and other
7.9support facilities. For purposes of this subdivision, "computer software" includes, but is not
7.10limited to, software utilized or loaded at a qualified data center, qualified refurbished data
7.11center, or qualified large-scale data center, including maintenance, licensing, and software
7.12customization.
7.13 deleted text begin (c) deleted text end new text begin (d) new text end For purposes of this subdivision, a "qualified refurbished data center" means an
7.14existing facility that qualifies as a data center under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , clauses (2) and (3),
7.15but that is comprised of one or more buildings that consist in the aggregate of at least 25,000
7.16square feet, and that are located on a single parcel or contiguous parcels, where the total
7.17cost of construction or refurbishment, investment in enterprise information technology
7.18equipment, and computer software is at least $50,000,000 within a 24-month period.
7.19 deleted text begin (d) deleted text end new text begin (e) new text end For purposes of this subdivision, "enterprise information technology equipment"
7.20means computers and equipment supporting computing, networking, or data storage,
7.21including servers and routers. It includes, but is not limited to: cooling systems, cooling
7.22towers, and other temperature control infrastructure; power infrastructure for transformation,
7.23distribution, or management of electricity used for the maintenance and operation of a
7.24qualified data center or qualified refurbished data center, including but not limited to exterior
7.25dedicated business-owned substations, backup power generation systems, battery systems,
7.26and related infrastructure; and racking systems, cabling, and trays, which are necessary for
7.27the maintenance and operation of the qualified data center, qualified refurbished data center,
7.28or qualified large-scale data center.
7.29 deleted text begin (e) deleted text end new text begin (f) new text end For purposes of this subdivision, "qualified large-scale data center" means a
7.30facility in Minnesota:
7.31(1) that is comprised of one or more buildings connected to each other by fiber and
7.32associated equipment that consist in the aggregate of at least 25,000 square feet, and that
7.33are located in one physical location or multiple locations; and
8.1(2) for which the total cost of construction or refurbishment, investment in enterprise
8.2information technology equipment, and computer software is at least $250,000,000
8.3collectively by the facility and its tenants within a 60-month period beginning after June
8.430, 2025.
8.5 deleted text begin (f) deleted text end new text begin (g) new text end A qualified data center, qualified large-scale data center, or qualified refurbished
8.6data center may claim the exemptions in this subdivision for purchases made within 35
8.7years of the date of its first purchase qualifying for the exemption under paragraph (a).
8.8 deleted text begin (g) deleted text end new text begin (h) new text end The exemption in this subdivision is allowed for qualified data centers, qualified
8.9large-scale data centers, and qualified refurbished data centers that were certified under
8.10paragraph deleted text begin (h) deleted text end new text begin (i) new text end before July 1, 2042.
8.11 deleted text begin (h) deleted text end new text begin (i) new text end The commissioner of employment and economic development must certify to the
8.12commissioner of revenue, in a format approved by the commissioner of revenue, when a
8.13qualified data center has met the requirements under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , a qualified refurbished
8.14data center has met the requirements under paragraph deleted text begin (c) deleted text end new text begin (d) new text end , or a qualified large-scale data
8.15center has met the requirements under paragraph deleted text begin (e) deleted text end new text begin (f) new text end . The certification must provide the
8.16following information regarding each qualified data center or qualified refurbished data
8.17center:
8.18(1) the total square footage amount;
8.19(2) the total amount of construction or refurbishment costs and the total amount of
8.20qualifying investments in enterprise information technology equipment and computer
8.21software;
8.22(3) the beginning and ending of the applicable period under paragraph deleted text begin (b), (c), or (e) deleted text end
8.23 new text begin (c), (d), or (f) new text end in which the qualifying expenditures and purchases under clause (2) were
8.24made, but in no case shall the period begin before July 1, 2012; and
8.25(4) the date upon which the qualified data center first met the requirements under
8.26paragraph deleted text begin (b) deleted text end new text begin (c) new text end , a qualified refurbished data center first met the requirements under
8.27paragraph deleted text begin (c) deleted text end new text begin (d) new text end , or a qualified large-scale data center first met the requirements under
8.28paragraph deleted text begin (e) deleted text end new text begin (f) new text end .
8.29 deleted text begin (i) deleted text end new text begin (j) new text end Any refund for sales tax paid on qualifying purchases under this subdivision must
8.30not be issued unless the commissioner of revenue has received the certification required
8.31under paragraph deleted text begin (h) deleted text end new text begin (i) new text end issued by the commissioner of employment and economic
8.32development.
9.1 deleted text begin (j) deleted text end new text begin (k) new text end The commissioner of employment and economic development must annually
9.2notify the commissioner of revenue of the qualified data centers that are projected to meet
9.3the requirements under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , the qualified refurbished data centers that are
9.4projected to meet the requirements under paragraph deleted text begin (c) deleted text end new text begin (d) new text end , and the qualified large-scale
9.5data centers that are projected to meet the requirements under paragraph deleted text begin (e) deleted text end new text begin (f) new text end , in each of
9.6the next four years. The notification must provide the information required under paragraph
9.7 deleted text begin (h) deleted text end new text begin (i) new text end , clauses (1) to (4), for each qualified data center, qualified refurbished data center,
9.8or qualified large-scale data center.
9.9 deleted text begin (k) deleted text end new text begin (l) new text end Laborers and mechanics performing work to construct or refurbish qualified
9.10large-scale data centers must be paid the prevailing wage rate for the work as defined in
9.11section 177.42, subdivision 6. Work performed to construct or refurbish qualified large-scale
9.12data centers is subject to the requirements and enforcement provisions of sections 177.27,
9.13177.30, 177.32, and 177.41 to 177.45. For purposes of this paragraph, "refurbish" does not
9.14include maintenance or equipment refreshment or replacement. The commissioner of
9.15employment and economic development must not certify a qualified large-scale data center
9.16under paragraph deleted text begin (h) deleted text end new text begin (i) new text end unless the entity seeking an exemption certifies to the commissioner
9.17of employment and economic development that it has complied with this paragraph for all
9.18covered work after June 30, 2025.
9.19 deleted text begin (l) deleted text end new text begin (m) new text end Within three years after being placed in service, a qualified large-scale data center
9.20must certify to the commissioner of commerce that the facility has attained certification
9.21under one or more of the following sustainable design or green building standards:
9.22(1) BREEAM for new construction or BREEAM in-use;
9.23(2) Energy Star;
9.24(3) Envision;
9.25(4) ISO 50001-energy management;
9.26(5) LEED for building design and construction or LEED for operations and maintenance;
9.27(6) green globes for new construction or green globes for existing buildings;
9.28(7) UL 3223; or
9.29(8) other reasonable standards approved by the commissioner of employment and
9.30economic development.
9.31 deleted text begin (m) deleted text end new text begin (n) new text end Notwithstanding section 289A.38, subdivision 1, the amount of the exemption
9.32allowed to a qualified large-scale data center must be repaid to the commissioner of revenue
10.1if the commissioner of commerce determines that a qualified large-scale data center has not
10.2met the requirements under paragraph deleted text begin (l) deleted text end new text begin (m) new text end . Nothing in this paragraph prohibits the
10.3commissioner of revenue from making an assessment of tax, interest, or penalties if the
10.4commissioner of revenue determines that sales to and purchases made by a qualified
10.5large-scale data center do not qualify for the exemption under this subdivision.
10.6 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.
Progress through the legislative process
In Committee