SF1970

Procedures modification governing cost recovery for public utility electric generation and transmission assets
Legislative Session 94 (2025-2026)

Related bill: HF1311

Bill text

Introduction

ReadChanges
PDF
(underlined = new law, struck through = current law the bill removes)
1.1A bill for an act
1.2relating to energy; modifying procedures governing cost recovery for public utility
1.3electric generation and transmission assets; amending Minnesota Statutes 2024,
1.4section 216B.16, by adding subdivisions.
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.6Section 1. Minnesota Statutes 2024, section 216B.16, is amended by adding a subdivision
1.7to read:
1.8 new text begin Subd. 6e. Cost recovery for generation and transmission assets. (a) A public utility new text end
1.9 new text begin that proposes to add an electric generating facility or transmission asset to the public utility's new text end
1.10 new text begin rate base must include in the filing with the commission (1) a quantitative and qualitative new text end
1.11 new text begin assessment of the proposed asset's contribution to the utility's system reliability during times new text end
1.12 new text begin of peak demand, and (2) for an electric generating facility, a calculation of the addition's new text end
1.13 new text begin seasonal effective load carrying capability and the methodology used to make the calculation. new text end
1.14 new text begin (b) A commission order addressing the addition of an electric generating facility or new text end
1.15 new text begin transmission asset to a public utility's rate base must: new text end
1.16 new text begin (1) include a finding explaining the extent to which adding the electric generating facility new text end
1.17 new text begin or transmission asset contributes to the utility's system reliability during times of peak new text end
1.18 new text begin demand, as determined by the commission; new text end
1.19 new text begin (2) determine what, if any, portion of the costs and expenses related to adding the electric new text end
1.20 new text begin generating unit or transmission asset to the public utility's rate base are recoverable costs new text end
1.21 new text begin that may be obtained through rates that are just and reasonable; and new text end
1.22 new text begin (3) include the following information, as applicable: new text end
2.1 new text begin (i) the approved increase in recoverable rates; new text end
2.2 new text begin (ii) the approved rate of return on an electric generating facility or transmission asset, new text end
2.3 new text begin and the duration of the approved return; and new text end
2.4 new text begin (iii) the amount of the electric generating facility or transmission asset costs and expenses new text end
2.5 new text begin that the commission has determined are not recoverable costs. new text end
2.6 new text begin (c) For the purposes of this subdivision and subdivision 6f, the following terms have the new text end
2.7 new text begin meanings given: new text end
2.8 new text begin (1) "electric generating facility" means an asset used to generate or store electricity for new text end
2.9 new text begin retail sale to Minnesota ratepayers; new text end
2.10 new text begin (2) "recoverable costs" means the revenue a public utility may recover from Minnesota new text end
2.11 new text begin ratepayers to pay for: new text end
2.12 new text begin (i) the cost of an electric generating facility; new text end
2.13 new text begin (ii) the cost of a transmission asset; and new text end
2.14 new text begin (iii) the rate of return a public utility may earn on items (i) and (ii); new text end
2.15 new text begin (3) "seasonal effective load carrying capability" means the incremental load an electric new text end
2.16 new text begin system is capable of supplying from a particular electric generating facility while maintaining new text end
2.17 new text begin the same level of system reliability during each season, as determined by the Midcontinent new text end
2.18 new text begin Independent System Operator; new text end
2.19 new text begin (4) "system reliability" means an electric system's ability to deliver electricity to the new text end
2.20 new text begin electric system's customers without interruption or failure; and new text end
2.21 new text begin (5) "transmission asset" means equipment necessary to transmit electricity from an new text end
2.22 new text begin electric generating facility to a public utility's distribution system for delivery to a retail new text end
2.23 new text begin electric customer. new text end
2.24 new text begin EFFECTIVE DATE. This section is effective the day following final enactment and new text end
2.25 new text begin applies to applicable filings made on or after that date. new text end
2.26Sec. 2. Minnesota Statutes 2024, section 216B.16, is amended by adding a subdivision to
2.27read:
2.28 new text begin Subd. 6f. Reduction in capacity or retirement of generation or transmission assets. (a) new text end
2.29 new text begin A public utility that proposes to reduce the capacity of or retire from service an electric new text end
2.30 new text begin generating facility or a transmission asset must include in the public utility's filing with the new text end
2.31 new text begin commission evidence that the proposed action does not impair the public utility's ability to new text end
3.1 new text begin fully meet the public utility's system reliability requirements during times of peak demand, new text end
3.2 new text begin including a quantitative and qualitative evaluation of the impact of the proposed action on new text end
3.3 new text begin system reliability. new text end
3.4 new text begin (b) A commission order addressing the reduction in capacity or retirement of an electric new text end
3.5 new text begin generating facility or transmission facility must contain an explanation describing the extent new text end
3.6 new text begin to which the action impacts the utility's system reliability during times of peak demand, new text end
3.7 new text begin taking into account other scheduled utility asset reductions in capacity or retirements from new text end
3.8 new text begin service. new text end
3.9 new text begin EFFECTIVE DATE. This section is effective the day following final enactment and new text end
3.10 new text begin applies to applicable filings made on or after that date. new text end

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.