1.1A bill for an act
1.2relating to data centers; modifying the criteria for preapplication evaluations of
1.3water appropriations for certain data centers; exempting certain data centers'
1.4electricity sales in calculating a utility's solar energy standard; exempting certain
1.5data centers from paying a fee; exempting certain data centers from paying sales
1.6tax on electricity purchases; providing for data center energy generation
1.7redundancy; amending Minnesota Statutes 2024, sections 116D.04, subdivision
1.84a; 216B.02, by adding a subdivision; 216B.243, subdivision 8; 216I.02, by adding
1.9a subdivision; 216I.07, subdivision 2; Minnesota Statutes 2025 Supplement, sections
1.10103G.265, subdivision 5; 216B.02, subdivision 12; 216B.1623; 216B.1691,
1.11subdivision 2f; 216B.72; 216I.07, subdivision 3; 297A.68, subdivision 42.
1.12BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.13Section 1. Minnesota Statutes 2025 Supplement, section 103G.265, subdivision 5, is
1.14amended to read:
1.15Subd. 5. Preapplication evaluation of certain water appropriation projects. (a) This
1.16subdivision applies to a data center, as defined in section 216B.02, subdivision 11, whose
1.17proposed new text begin net increase in new text end consumptive use exceeds 100,000,000 gallons per year and which
1.18requires a permit amendment or a new individual permit.
1.19(b) In response to a contact from a data center regarding a project that is likely to be
1.20subject to this subdivision, the department may request preapplication information from the
1.21data center that is helpful in assisting the department to assess the factors affecting the ability
1.22of a water source to meet a project's water use needs at a proposed location, including:
1.23(1) a project description;
1.24(2) the project's estimated water use rates and volumes for the maximum day, maximum
1.25month, and average year;
2.1(3) the anticipated source of water; and
2.2(4) water quality or temperature requirements.
2.3(c) The department may request any additional information necessary from the data
2.4center to assist it to assess the ability of a water source to meet a project's water use needs.
2.5(d) The commissioner shall evaluate the information supplied under this subdivision
2.6and shall respond in writing, which may be electronically transmitted, describing potential
2.7water availability constraints at each proposed project site.
2.8(e) In determining the impact of a potential project on water quality and quantity, the
2.9commissioner may consult with the commissioners of health, agriculture, and the Pollution
2.10Control Agency, and other state agencies.
2.11(f) Any communication made or information exchanged under this subdivision between
2.12a data center and a government agency, or between government agencies, is nonpublic data,
2.13as defined in section 13.02, subdivision 9.
2.14(g) None of the discussions, filings, or evaluations made under this subdivision preclude
2.15or supplant environment review, preliminary well-construction approval, appropriation
2.16permit review, or any other requirements under federal, state, or local law.
2.17 new text begin (h) For purposes of this subdivision, "net increase in consumptive use" means the new text end
2.18 new text begin estimated net increase in annual water consumption by a data center after subtracting new text end
2.19 new text begin documented reductions in consumption from the same water source by other entities that new text end
2.20 new text begin occurred within the past ... years or are scheduled to occur within ... years of the date the new text end
2.21 new text begin data center initiates operations. new text end
2.22 new text begin (i) This section does not apply to a qualified large-scale data center, as defined in section new text end
2.23 new text begin 297A.68, subdivision 42, that: new text end
2.24 new text begin (1) files an application on or before January 1, 2035, with a county, town, or municipality new text end
2.25 new text begin for a permit or approval that is necessary to allow for construction; or new text end
2.26 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
2.27 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
2.28Sec. 2. Minnesota Statutes 2024, section 116D.04, subdivision 4a, is amended to read:
2.29Subd. 4a. Alternative review. new text begin (a) new text end The board shall by rule identify alternative forms of
2.30environmental review which will address the same issues and utilize similar procedures as
3.1an environmental impact statement in a more timely or more efficient manner to be utilized
3.2in lieu of an environmental impact statement.
3.3 new text begin (b) Upon adoption by the responsible governmental unit of the environmental document new text end
3.4 new text begin and plan for mitigation under an alternative urban areawide review process, and new text end
3.5 new text begin notwithstanding additional environmental review that may otherwise be required for a new text end
3.6 new text begin phased action, connected action, or project component that was not evaluated in the new text end
3.7 new text begin alternative urban areawide review process, environmental review is complete and the new text end
3.8 new text begin prerequisites under subdivision 2b are satisfied with respect to the anticipated residential, new text end
3.9 new text begin commercial, warehousing, and light industrial development projects that are consistent with new text end
3.10 new text begin development assumptions within the established boundaries of the geographic area to which new text end
3.11 new text begin the alternative urban areawide review applies. new text end
3.12 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.13Sec. 3. Minnesota Statutes 2025 Supplement, section 216B.02, subdivision 12, is amended
3.14to read:
3.15Subd. 12. Qualified large-scale data center. "Qualified large-scale data center" has the
3.16meaning given in section 297A.68, subdivision 42 deleted text begin , paragraph (e) deleted text end .
3.17 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.18Sec. 4. Minnesota Statutes 2024, section 216B.02, is amended by adding a subdivision to
3.19read:
3.20 new text begin Subd. 13. Emergency backup generator. "Emergency backup generator" means a new text end
3.21 new text begin stationary compressed ignition or spark ignition engine described under Code of Federal new text end
3.22 new text begin Regulations, title 40, parts 60.4211(f) and 60.4243(d), respectively, installed with equipment new text end
3.23 new text begin that prevents the flow of electricity to the electric grid. new text end
3.24Sec. 5. Minnesota Statutes 2025 Supplement, section 216B.1623, is amended to read:
3.25216B.1623 CLEAN ENERGY AND CAPACITY TARIFF.
3.26 new text begin Subdivision 1. Tariff offer. new text end The commission shall require each public utility to offer a
3.27clean energy and capacity tariff for commercial and industrial customers. The clean energy
3.28and capacity tariff shall require a special contract between the utility and one or more
3.29customers that shall:
3.30(1) be optional for participating customers;
4.1(2) permit participating customers to elect to serve some or all of their energy or capacity
4.2usage from new clean energy or capacity resources as long as reliability is maintained;
4.3(3) require the participating customers to pay all proportional costs associated with the
4.4addition of the new clean energy or capacity resources, including any utility costs caused
4.5by the addition of the new clean energy or capacity resources to the grid;
4.6(4) develop an appropriate energy and capacity credit;
4.7(5) prohibit cost shifting from the participating customers to other utility customers or
4.8vice versa; and
4.9(6) allow a utility with an applicable tariff on file to demonstrate their existing tariff's
4.10compliance with this section.
4.11 new text begin Subd. 2. Exemptions. This subdivision does not apply to a qualified large-scale data new text end
4.12 new text begin center that: new text end
4.13 new text begin (1) files an application on or before January 1, 2035, with a county, town, or municipality new text end
4.14 new text begin for a permit or approval that is necessary to allow for construction; or new text end
4.15 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
4.16 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
4.17Sec. 6. Minnesota Statutes 2025 Supplement, section 216B.1691, subdivision 2f, is amended
4.18to read:
4.19Subd. 2f. Solar energy standard. (a) In addition to the requirements of subdivisions 2a
4.20and 2g, each public utility shall generate or procure sufficient electricity generated by solar
4.21energy to serve its retail electricity customers in Minnesota so that by the end of 2020, at
4.22least 1.5 percent of the utility's total retail electric sales to retail customers in Minnesota is
4.23generated by solar energy.
4.24(b) For a public utility with more than 200,000 retail electric customers, at least ten
4.25percent of the 1.5 percent goal must be met by solar energy generated by or procured from
4.26solar photovoltaic devices with a nameplate capacity of 40 kilowatts or less.
4.27(c) A public utility with between 50,000 and 200,000 retail electric customers:
4.28(1) must meet at least ten percent of the 1.5 percent goal with solar energy generated by
4.29or procured from solar photovoltaic devices with a nameplate capacity of 40 kilowatts or
4.30less; and
5.1(2) may apply toward the ten percent goal in clause (1) individual customer subscriptions
5.2of 40 kilowatts or less to a community solar garden program operated by the public utility
5.3that has been approved by the commission.
5.4(d) The solar energy standard established in this subdivision is subject to all the provisions
5.5of this section governing a utility's standard obligation under subdivision 2a.
5.6(e) It is an energy goal of the state of Minnesota that, by 2030, ten percent of the retail
5.7electric sales in Minnesota be generated by solar energy.
5.8(f) For the purposes of calculating the total retail electric sales of a public utility deleted text begin serving deleted text end
5.9 deleted text begin fewer than 200,000 retail electric customers deleted text end under this subdivision, there shall be excluded
5.10retail electric sales to customers that are:
5.11 new text begin (1) served by a public utility with fewer than 200,000 retail electric customers and are: new text end
5.12 deleted text begin (1) deleted text end new text begin (i) new text end an iron mining extraction and processing facility, including a scram mining facility
5.13as defined in Minnesota Rules, part 6130.0100, subpart 16;
5.14 deleted text begin (2) deleted text end new text begin (ii) new text end a qualified large-scale data center; or
5.15 deleted text begin (3) deleted text end new text begin (iii) new text end a paper mill, wood products manufacturer, sawmill, or oriented strand board
5.16manufacturer deleted text begin . deleted text end new text begin ; or new text end
5.17 new text begin (2) a qualified large-scale data center that: new text end
5.18 new text begin (i) files an application on or before January 1, 2035, with a county, town, or municipality new text end
5.19 new text begin for a permit or approval that is necessary to allow for construction; or new text end
5.20 new text begin (ii) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
5.21 deleted text begin Those deleted text end new text begin (g) The new text end customers new text begin identified in paragraph (f), clause (1) or (2), new text end may not have
5.22included in the rates charged to them by the public utility deleted text begin serving fewer than 200,000 retail deleted text end
5.23 deleted text begin electric customers deleted text end any costs of satisfying the solar standard specified by this subdivision.
5.24 deleted text begin (g) deleted text end new text begin (h) new text end A public utility may not use energy used to satisfy the solar energy standard under
5.25this subdivision to satisfy its standard obligation under subdivision 2a. A public utility may
5.26not use energy used to satisfy the standard obligation under subdivision 2a to satisfy the
5.27solar standard under this subdivision.
5.28 deleted text begin (h) deleted text end new text begin (i) new text end Notwithstanding any law to the contrary, a solar renewable energy credit associated
5.29with a solar photovoltaic device installed and generating electricity in Minnesota after
5.30August 1, 2013, but before 2020 may be used to meet the solar energy standard established
5.31under this subdivision.
6.1 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
6.2Sec. 7. Minnesota Statutes 2024, section 216B.243, subdivision 8, is amended to read:
6.3Subd. 8. Exemptions. (a) This section does not apply to:
6.4(1) cogeneration or small power production facilities as defined in the Federal Power
6.5Act, United States Code, title 16, section 796, paragraph (17), subparagraph (A), and
6.6paragraph (18), subparagraph (A), and having a combined capacity at a single site of less
6.7than 80,000 kilowatts; plants or facilities for the production of ethanol or fuel alcohol; or
6.8any case where the commission has determined after being advised by the attorney general
6.9that its application has been preempted by federal law;
6.10(2) a high-voltage transmission line proposed primarily to distribute electricity to serve
6.11the demand of a single customer at a single location, unless the applicant opts to request
6.12that the commission determine need under this section or section 216B.2425;
6.13(3) the upgrade to a higher voltage of an existing transmission line that serves the demand
6.14of a single customer that primarily uses existing rights-of-way, unless the applicant opts to
6.15request that the commission determine need under this section or section 216B.2425;
6.16(4) a high-voltage transmission line of one mile or less required to connect a new or
6.17upgraded substation to an existing, new, or upgraded high-voltage transmission line;
6.18(5) conversion of the fuel source of an existing electric generating plant to using natural
6.19gas;
6.20(6) the modification of an existing electric generating plant to increase efficiency, as
6.21long as the capacity of the plant is not increased more than ten percent or more than 100
6.22megawatts, whichever is greater;
6.23(7) a large wind energy conversion system, as defined in section 216I.02, subdivision
6.2412, or a solar energy generating system, as defined in section 216I.02, subdivision 18, for
6.25which a site permit application is submitted by an independent power producer under chapter
6.26216I;
6.27(8) a large wind energy conversion system, as defined in section 216I.02, subdivision
6.2812, or a solar energy generating system, as defined in section 216I.02, subdivision 18,
6.29engaging in a repowering project that:
6.30(i) will not result in the system exceeding the nameplate capacity under its most recent
6.31interconnection agreement; or
7.1(ii) will result in the system exceeding the nameplate capacity under its most recent
7.2interconnection agreement, provided that the Midcontinent Independent System Operator
7.3has provided a signed generator interconnection agreement that reflects the expected net
7.4power increase;
7.5(9) energy storage systems, as defined in section 216I.02, subdivision 6;
7.6(10) transmission lines that directly interconnect large wind energy conversion systems,
7.7solar energy generating systems, or energy storage systems to the transmission system; deleted text begin or deleted text end
7.8(11) relocation of an existing high voltage transmission line to new right-of-way, provided
7.9that any new structures that are installed are not designed for and capable of operation at
7.10higher voltage deleted text begin . deleted text end new text begin ; or new text end
7.11 new text begin (12) a combination of emergency backup generators at a single site with a combined new text end
7.12 new text begin capacity of 50,000 kilowatts or more that provides power to a data center and is eligible for new text end
7.13 new text begin permitting as a single stationary source under Minnesota Rules, part 7007.0200, 7007.0250, new text end
7.14 new text begin 7007.1100, or 7007.1110 to 7007.1141. new text end
7.15(b) For the purpose of this subdivision, "repowering project" means:
7.16(1) modifying a large wind energy conversion system or a solar energy generating system
7.17that is a large energy facility to increase its efficiency without increasing its nameplate
7.18capacity;
7.19(2) replacing turbines in a large wind energy conversion system without increasing the
7.20nameplate capacity of the system; or
7.21(3) increasing the nameplate capacity of a large wind energy conversion system.
7.22 new text begin EFFECTIVE DATE; APPLICATION. This section is effective the day following new text end
7.23 new text begin final enactment and applies to applications under Minnesota Statutes, section 216B.243, new text end
7.24 new text begin that are pending before or submitted to the Public Utilities Commission on or after that date. new text end
7.25Sec. 8. Minnesota Statutes 2025 Supplement, section 216B.72, is amended to read:
7.26216B.72 QUALIFIED LARGE-SCALE DATA CENTER FEE.
7.27(a) new text begin Except as provided in paragraph (d), new text end the commissioner must collect an annual fee
7.28from deleted text begin the deleted text end new text begin a new text end qualified large-scale data center deleted text begin , deleted text end on a schedule prescribed by the commissioner
7.29and deleted text begin deposited deleted text end new text begin must deposit the fee new text end in the energy and conservation account established in
7.30section 216B.241, subdivision 2a.
8.1(b) The fee is based on deleted text begin the deleted text end new text begin a new text end qualified large-scale data center's peak demand the utility
8.2arranges to serve, reflecting the qualified large-scale data center's peak demand forecast
8.3provided to the utility, expressed in megawatts (MW), as follows:
8.4Peak Demand Fee
8.5(1) 100 to 250 MW $2,000,000
8.6(2) above 250 MW but below 500 MW $3,000,000
8.7(3) 500 MW but below 750 MW $4,000,000
8.8(4) 750 MW or greater $5,000,000
8.9(c) The fee data collected under this section must be treated as nonpublic data, as defined
8.10under section 13.02, subdivision 9.
8.11 new text begin (d) This section does not apply to a qualified large-scale data center that: new text end
8.12 new text begin (1) files an application on or before January 1, 2035, with a county, town, or municipality new text end
8.13 new text begin for a permit or approval that is necessary to allow for construction; or new text end
8.14 new text begin (2) is located in an eligible community, as defined in section 116J.55, subdivision 1. new text end
8.15 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
8.16Sec. 9. Minnesota Statutes 2024, section 216I.02, is amended by adding a subdivision to
8.17read:
8.18 new text begin Subd. 5a. Emergency backup generator. "Emergency backup generator" has the new text end
8.19 new text begin meaning given in section 216B.02, subdivision 13. new text end
8.20 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
8.21Sec. 10. Minnesota Statutes 2024, section 216I.07, subdivision 2, is amended to read:
8.22Subd. 2. Applicable projects. The requirements and procedures under this section apply
8.23to projects for which the applicant's proposal is:
8.24(1) large electric power generating plants with a capacity of less than 80 megawatts;
8.25 new text begin (2) a combination of emergency backup generators designed to serve one person and new text end
8.26 new text begin located on property owned or controlled by the person that is contiguous with the facility new text end
8.27 new text begin the emergency backup generators serve; new text end
8.28 deleted text begin (2) deleted text end new text begin (3) new text end large electric power generating plants that are fueled by natural gas;
8.29 deleted text begin (3) deleted text end new text begin (4) new text end high-voltage transmission lines with a capacity between 100 and 300 kilovolts;
9.1 deleted text begin (4) deleted text end new text begin (5) new text end high-voltage transmission lines with a capacity in excess of 300 kilovolts and
9.2less than 30 miles in length in Minnesota;
9.3 deleted text begin (5) deleted text end new text begin (6) new text end high-voltage transmission lines with a capacity in excess of 300 kilovolts, if at
9.4least 80 percent of the distance of the line in Minnesota, as proposed by the applicant, is
9.5located along existing high-voltage transmission line right-of-way;
9.6 deleted text begin (6) deleted text end new text begin (7) new text end solar energy systems;
9.7 deleted text begin (7) deleted text end new text begin (8) new text end energy storage systems; and
9.8 deleted text begin (8) deleted text end new text begin (9) new text end large wind energy conversion systems.
9.9 new text begin EFFECTIVE DATE; APPLICATION. This section is effective July 1, 2026, and new text end
9.10 new text begin applies to applications under Minnesota Statutes, section 216I.07, that are pending before new text end
9.11 new text begin or submitted to the Public Utilities Commission on or after that date. new text end
9.12Sec. 11. Minnesota Statutes 2025 Supplement, section 216I.07, subdivision 3, is amended
9.13to read:
9.14Subd. 3. Environmental review. (a) For the projects identified in subdivision 2 and
9.15following the procedures under this section, the applicant must prepare and submit an
9.16environmental assessment with the application. A draft of the environmental assessment
9.17must also be provided to commission staff as part of the preapplication review under section
9.18216I.05, subdivision 6. The environmental assessment must (1) contain information regarding
9.19the proposed project's human and environmental impacts, and (2) address mitigating measures
9.20for identified impacts. new text begin The environmental assessment for projects identified in subdivision new text end
9.21 new text begin 2, clause (2), must include a discussion of reasonable alternatives to the proposed project new text end
9.22 new text begin that considers: (i) the appropriateness of the size and type of the proposed method of new text end
9.23 new text begin generation compared to those of reasonable alternatives; (ii) the cost to the proposer of new text end
9.24 new text begin energy that would be supplied by the project compared to the cost of energy that would be new text end
9.25 new text begin supplied by reasonable alternatives; (iii) the effect of the proposed project upon the natural new text end
9.26 new text begin and socioeconomic environments compared to the effect of reasonable alternatives; and (iv) new text end
9.27 new text begin the expected reliability of the proposed facility compared to the expected reliability of new text end
9.28 new text begin reasonable alternatives. new text end The environmental assessment is the only state environmental
9.29review document that must be prepared for the proposed project.
9.30(b) If after the public meeting the commission identifies other sites or routes or potential
9.31impacts for review, the commission must prepare an addendum to the environmental
9.32assessment that evaluates (1) the human and environmental impacts of the alternative site
9.33or route, and (2) any additional mitigating measures related to the identified impacts
10.1consistent with the scoping decision made pursuant to section 216I.05, subdivision 10,
10.2clause (2). The public may provide comments on the environmental assessment and any
10.3addendum to the environmental assessment at the public hearing and comment period under
10.4subdivision 4. When making the commission's final decision, the commission must consider
10.5the environmental assessment, the environmental assessment addendum, if any, and the
10.6entirety of the record related to human and environmental impacts.
10.7Sec. 12. Minnesota Statutes 2025 Supplement, section 297A.68, subdivision 42, is amended
10.8to read:
10.9Subd. 42. Data centers. (a) Purchases of enterprise information technology equipment
10.10and computer software for use in a qualified data center, a qualified refurbished data center,
10.11or a qualified large-scale data center are exempt, except that computer software maintenance
10.12agreements are exempt for purchases made after June 30, 2013. The tax on purchases exempt
10.13under this paragraph must be imposed and collected as if the rate under section 297A.62,
10.14subdivision 1, applied, and then refunded after June 30, 2013, in the manner provided in
10.15section 297A.75. This exemption includes enterprise information technology equipment
10.16and computer software purchased to replace or upgrade enterprise information technology
10.17equipment and computer software in a qualified data center, a qualified refurbished data
10.18center, or a qualified large-scale data center.
10.19 new text begin (b) Purchases of electricity used or consumed to operate a qualified large-scale data new text end
10.20 new text begin center located in an eligible community, as defined in section 116J.55, subdivision 1, are new text end
10.21 new text begin exempt. new text end
10.22 deleted text begin (b) deleted text end new text begin (c) new text end For purposes of this subdivision, "qualified data center" means a facility in
10.23Minnesota:
10.24(1) that is comprised of one or more buildings that consist in the aggregate of at least
10.2525,000 square feet, and that are located on a single parcel or on contiguous parcels, where
10.26the total cost of construction or refurbishment, investment in enterprise information
10.27technology equipment, and computer software is at least $30,000,000 within a 48-month
10.28period. The 48-month period begins no sooner than July 1, 2012, except that costs for
10.29computer software maintenance agreements purchased before July 1, 2013, are not included
10.30in determining if the $30,000,000 threshold has been met;
10.31(2) that is constructed or substantially refurbished after June 30, 2012, where
10.32"substantially refurbished" means that at least 25,000 square feet have been rebuilt or
10.33modified, including:
11.1(i) installation of enterprise information technology equipment; environmental control,
11.2computer software, and energy efficiency improvements; and
11.3(ii) building improvements; and
11.4(3) that is used to house enterprise information technology equipment, where the facility
11.5has the following characteristics:
11.6(i) uninterruptible power supplies, generator backup power, or both;
11.7(ii) sophisticated fire suppression and prevention systems; and
11.8(iii) enhanced security. A facility will be considered to have enhanced security if it has
11.9restricted access to the facility to selected personnel; permanent security guards; video
11.10camera surveillance; an electronic system requiring pass codes, keycards, or biometric scans,
11.11such as hand scans and retinal or fingerprint recognition; or similar security features.
11.12In determining whether the facility has the required square footage, the square footage
11.13of the following spaces shall be included if the spaces support the operation of enterprise
11.14information technology equipment: office space, meeting space, and mechanical and other
11.15support facilities. For purposes of this subdivision, "computer software" includes, but is not
11.16limited to, software utilized or loaded at a qualified data center, qualified refurbished data
11.17center, or qualified large-scale data center, including maintenance, licensing, and software
11.18customization.
11.19 deleted text begin (c) deleted text end new text begin (d) new text end For purposes of this subdivision, a "qualified refurbished data center" means an
11.20existing facility that qualifies as a data center under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , clauses (2) and (3),
11.21but that is comprised of one or more buildings that consist in the aggregate of at least 25,000
11.22square feet, and that are located on a single parcel or contiguous parcels, where the total
11.23cost of construction or refurbishment, investment in enterprise information technology
11.24equipment, and computer software is at least $50,000,000 within a 24-month period.
11.25 deleted text begin (d) deleted text end new text begin (e) new text end For purposes of this subdivision, "enterprise information technology equipment"
11.26means computers and equipment supporting computing, networking, or data storage,
11.27including servers and routers. It includes, but is not limited to: cooling systems, cooling
11.28towers, and other temperature control infrastructure; power infrastructure for transformation,
11.29distribution, or management of electricity used for the maintenance and operation of a
11.30qualified data center or qualified refurbished data center, including but not limited to exterior
11.31dedicated business-owned substations, backup power generation systems, battery systems,
11.32and related infrastructure; and racking systems, cabling, and trays, which are necessary for
12.1the maintenance and operation of the qualified data center, qualified refurbished data center,
12.2or qualified large-scale data center.
12.3 deleted text begin (e) deleted text end new text begin (f) new text end For purposes of this subdivision, "qualified large-scale data center" means a
12.4facility in Minnesota:
12.5(1) that is comprised of one or more buildings connected to each other by fiber and
12.6associated equipment that consist in the aggregate of at least 25,000 square feet, and that
12.7are located in one physical location or multiple locations; and
12.8(2) for which the total cost of construction or refurbishment, investment in enterprise
12.9information technology equipment, and computer software is at least $250,000,000
12.10collectively by the facility and its tenants within a 60-month period beginning after June
12.1130, 2025.
12.12 deleted text begin (f) deleted text end new text begin (g) new text end A qualified data center, qualified large-scale data center, or qualified refurbished
12.13data center may claim the exemptions in this subdivision for purchases made within 35
12.14years of the date of its first purchase qualifying for the exemption under paragraph (a).
12.15 deleted text begin (g) deleted text end new text begin (h) new text end The exemption in this subdivision is allowed for qualified data centers, qualified
12.16large-scale data centers, and qualified refurbished data centers that were certified under
12.17paragraph deleted text begin (h) deleted text end new text begin (i) new text end before July 1, 2042.
12.18 deleted text begin (h) deleted text end new text begin (i) new text end The commissioner of employment and economic development must certify to the
12.19commissioner of revenue, in a format approved by the commissioner of revenue, when a
12.20qualified data center has met the requirements under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , a qualified refurbished
12.21data center has met the requirements under paragraph deleted text begin (c) deleted text end new text begin (d) new text end , or a qualified large-scale data
12.22center has met the requirements under paragraph deleted text begin (e) deleted text end new text begin (f) new text end . The certification must provide the
12.23following information regarding each qualified data center or qualified refurbished data
12.24center:
12.25(1) the total square footage amount;
12.26(2) the total amount of construction or refurbishment costs and the total amount of
12.27qualifying investments in enterprise information technology equipment and computer
12.28software;
12.29(3) the beginning and ending of the applicable period under paragraph deleted text begin (b), (c), or (e) deleted text end
12.30 new text begin (c), (d), or (f) new text end in which the qualifying expenditures and purchases under clause (2) were
12.31made, but in no case shall the period begin before July 1, 2012; and
12.32(4) the date upon which the qualified data center first met the requirements under
12.33paragraph deleted text begin (b) deleted text end new text begin (c) new text end , a qualified refurbished data center first met the requirements under
13.1paragraph deleted text begin (c) deleted text end new text begin (d) new text end , or a qualified large-scale data center first met the requirements under
13.2paragraph deleted text begin (e) deleted text end new text begin (f) new text end .
13.3 deleted text begin (i) deleted text end new text begin (j) new text end Any refund for sales tax paid on qualifying purchases under this subdivision must
13.4not be issued unless the commissioner of revenue has received the certification required
13.5under paragraph deleted text begin (h) deleted text end new text begin (i) new text end issued by the commissioner of employment and economic
13.6development.
13.7 deleted text begin (j) deleted text end new text begin (k) new text end The commissioner of employment and economic development must annually
13.8notify the commissioner of revenue of the qualified data centers that are projected to meet
13.9the requirements under paragraph deleted text begin (b) deleted text end new text begin (c) new text end , the qualified refurbished data centers that are
13.10projected to meet the requirements under paragraph deleted text begin (c) deleted text end new text begin (d) new text end , and the qualified large-scale
13.11data centers that are projected to meet the requirements under paragraph deleted text begin (e) deleted text end new text begin (f) new text end , in each of
13.12the next four years. The notification must provide the information required under paragraph
13.13 deleted text begin (h) deleted text end new text begin (i) new text end , clauses (1) to (4), for each qualified data center, qualified refurbished data center,
13.14or qualified large-scale data center.
13.15 deleted text begin (k) deleted text end new text begin (l) new text end Laborers and mechanics performing work to construct or refurbish qualified
13.16large-scale data centers must be paid the prevailing wage rate for the work as defined in
13.17section 177.42, subdivision 6. Work performed to construct or refurbish qualified large-scale
13.18data centers is subject to the requirements and enforcement provisions of sections 177.27,
13.19177.30, 177.32, and 177.41 to 177.45. For purposes of this paragraph, "refurbish" does not
13.20include maintenance or equipment refreshment or replacement. The commissioner of
13.21employment and economic development must not certify a qualified large-scale data center
13.22under paragraph deleted text begin (h) deleted text end new text begin (i) new text end unless the entity seeking an exemption certifies to the commissioner
13.23of employment and economic development that it has complied with this paragraph for all
13.24covered work after June 30, 2025.
13.25 deleted text begin (l) deleted text end new text begin (m) new text end Within three years after being placed in service, a qualified large-scale data center
13.26must certify to the commissioner of commerce that the facility has attained certification
13.27under one or more of the following sustainable design or green building standards:
13.28(1) BREEAM for new construction or BREEAM in-use;
13.29(2) Energy Star;
13.30(3) Envision;
13.31(4) ISO 50001-energy management;
13.32(5) LEED for building design and construction or LEED for operations and maintenance;
13.33(6) green globes for new construction or green globes for existing buildings;
14.1(7) UL 3223; or
14.2(8) other reasonable standards approved by the commissioner of employment and
14.3economic development.
14.4 deleted text begin (m) deleted text end new text begin (n) new text end Notwithstanding section 289A.38, subdivision 1, the amount of the exemption
14.5allowed to a qualified large-scale data center must be repaid to the commissioner of revenue
14.6if the commissioner of commerce determines that a qualified large-scale data center has not
14.7met the requirements under paragraph deleted text begin (l) deleted text end new text begin (m) new text end . Nothing in this paragraph prohibits the
14.8commissioner of revenue from making an assessment of tax, interest, or penalties if the
14.9commissioner of revenue determines that sales to and purchases made by a qualified
14.10large-scale data center do not qualify for the exemption under this subdivision.
14.11 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.