HF4512

Public hearings and disclosures prior to approval of data center development required.
Legislative Session 94 (2025-2026)

Related bill: SF4296

Bill text

Introduction

ReadChanges
PDF
(underlined = new law, struck through = current law the bill removes)
1.1A bill for an act
1.2relating to local government; requiring public hearings and certain disclosures
1.3prior to approval of data center development; proposing coding for new law in
1.4Minnesota Statutes, chapter 462.
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.6Section 1. new text begin [462.3599] DATA CENTERS. new text end
1.7 new text begin Subdivision 1. Definitions. (a) For purposes of this section, the following terms have new text end
1.8 new text begin the meanings given. new text end
1.9 new text begin (b) "Armed with a firearm" has the meaning given in section 326.32, subdivision 1a. new text end
1.10 new text begin (c) "Armed with a weapon" has the meaning given in section 326.32, subdivision 1b. new text end
1.11 new text begin (d) "Data center" means a facility composed of one or more buildings that has a primary new text end
1.12 new text begin purpose of providing for the storage, management, or processing of digital data. new text end
1.13 new text begin (e) "End user" means the owner or operator of a constructed data center. new text end
1.14 new text begin (f) "Municipality" means a county, home rule charter or statutory city, or town. new text end
1.15 new text begin (g) "Security guard" has the meaning given in section 326.32, subdivision 13. new text end
1.16 new text begin Subd. 2. Public hearings required. A municipality must hold at least two public hearings new text end
1.17 new text begin prior to the approval of a rezoning petition or an application for a conditional use or special new text end
1.18 new text begin use permit made for the construction of a data center. new text end
1.19 new text begin Subd. 3. Disclosures required. (a) At least one public hearing under subdivision 2 must new text end
1.20 new text begin be solely for the purpose of informing the public of the petition or application. The new text end
2.1 new text begin municipality must disclose the following information at least 48 hours before the public new text end
2.2 new text begin hearing: new text end
2.3 new text begin (1) the name of the petitioner or applicant; new text end
2.4 new text begin (2) the name of the anticipated end user of the proposed data center; new text end
2.5 new text begin (3) the location and size of the proposed data center; new text end
2.6 new text begin (4) if the data center is located within or abuts an area zoned for residential use, the new text end
2.7 new text begin estimated number of security guards employed to protect the data center site during and new text end
2.8 new text begin after construction and whether any security guard will be armed with a firearm or armed new text end
2.9 new text begin with a weapon; and new text end
2.10 new text begin (5) the estimated scope of utilities necessary for operation of the proposed data center, new text end
2.11 new text begin including but not limited to fuel lines, sewer, stormwater, and electricity. new text end
2.12 new text begin (b) Forty-eight hours before any public meeting held to vote on approval of a petition new text end
2.13 new text begin or application, the municipality must disclose the information required under paragraph (a). new text end
2.14 new text begin (c) A municipality may make the disclosures required under this subdivision by posting new text end
2.15 new text begin the information on the municipality's website or by making the same information available new text end
2.16 new text begin for inspection at a reasonable time and place. new text end
2.17 new text begin Subd. 4. Effect of private agreements. The disclosure requirements under subdivision new text end
2.18 new text begin 3 apply notwithstanding any nondisclosure agreement or other contract signed by a new text end
2.19 new text begin municipality or an agent of a municipality. new text end
2.20 new text begin EFFECTIVE DATE. This section is effective August 1, 2026. new text end

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.