HF4236

Public utility interim rate amounts limited.
Legislative Session 94 (2025-2026)

Bill text

Introduction

ReadChanges
PDF
(underlined = new law, struck through = current law the bill removes)
1.1A bill for an act
1.2relating to energy; limiting public utility interim rate amounts; amending Minnesota
1.3Statutes 2024, section 216B.16, subdivision 3.
1.4BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.5Section 1. Minnesota Statutes 2024, section 216B.16, subdivision 3, is amended to read:
1.6Subd. 3. Interim rate. (a) Notwithstanding any order of suspension of a proposed
1.7increase in rates, the commission shall order an interim rate schedule into effect not later
1.8than 60 days after the initial filing date. The commission shall order the interim rate schedule
1.9ex parte without a public hearing. Notwithstanding the provisions of sections 216.25,
1.10216B.27, and 216B.52, no interim rate schedule ordered by the commission pursuant to this
1.11subdivision shall be subject to an application for a rehearing or an appeal to a court until
1.12the commission has rendered its final determination.
1.13(b) Unless the commission finds that exigent circumstances exist, the interim rate schedule
1.14shall be calculated using the proposed test year cost of capital, rate base, and expenses,
1.15except that it shall include: (1) a rate of return on common equity for the utility equal to
1.16that authorized by the commission in the utility's most recent rate proceeding; (2) rate base
1.17or expense items the same in nature and kind as those allowed by a currently effective order
1.18of the commission in the utility's most recent rate proceeding; and (3) no change in the
1.19existing rate design. In the case of a utility which has not been subject to a prior commission
1.20determination, the commission shall base the interim rate schedule on its most recent
1.21determination concerning a similar utility. new text begin An interim rate increase must not exceed five new text end
1.22 new text begin percent relative to the existing rate schedule. new text end
2.1(c) If, at the time of its final determination, the commission finds that the interim rates
2.2are in excess of the rates in the final determination, the commission shall order the utility
2.3to refund the excess amount collected under the interim rate schedule, including interest on
2.4it which shall be at the rate of interest determined by the commission. The utility shall
2.5commence distribution of the refund to its customers within 120 days of the final order, not
2.6subject to rehearing or appeal. If, at the time of its final determination, the commission finds
2.7that the interim rates are less than the rates in the final determination, the commission shall
2.8prescribe a method by which the utility will recover the difference in revenues between the
2.9date of the final determination and the date the new rate schedules are put into effect. In
2.10addition, when an extension is granted for settlement discussions under subdivision 1a, the
2.11commission shall allow the utility to also recover the difference in revenues for a length of
2.12time equal to the length of the extension.
2.13(d) If the public utility fails to make refunds within the period of time prescribed by the
2.14commission, the commission shall sue therefor and may recover on behalf of all persons
2.15entitled to a refund. In addition to the amount of the refund and interest due, the commission
2.16shall be entitled to recover reasonable attorney's fees, court costs and estimated cost of
2.17administering the distribution of the refund to persons entitled to it. No suit under this
2.18subdivision shall be maintained unless instituted within two years after the end of the period
2.19of time prescribed by the commission for repayment of refunds.
2.20(e) The commission shall not order an interim rate schedule in a general rate case into
2.21effect as provided by this subdivision until at least four months after it has made a final
2.22determination concerning any previously filed change of the rate schedule or the change
2.23has otherwise become effective under subdivision 2, unless:
2.24(1) the commission finds that a four-month delay would unreasonably burden the utility,
2.25its customers, or its shareholders and that an earlier imposition of interim rates is therefore
2.26necessary; or
2.27(2) the utility files a second general rate case at least 12 months after it has filed a previous
2.28general rate case for which the commission has extended the suspension period under
2.29subdivision 2.

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.

Progress through the legislative process

17%
In Committee
Loading…