1.1A bill for an act
1.2relating to energy; delaying the requirement for electric utilities to meet the
1.3renewable energy, solar, or carbon-free standard under certain conditions;
1.4prohibiting the demolition of fossil-fuel-powered electric generating plants under
1.5certain conditions; amending Minnesota Statutes 2024, section 216B.1691,
1.6subdivision 2b; proposing coding for new law in Minnesota Statutes, chapter 216B.
1.7BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.8Section 1. Minnesota Statutes 2024, section 216B.1691, subdivision 2b, is amended to
1.9read:
1.10Subd. 2b. Modification or delay of standard. (a) The commission shall modify or delay
1.11the implementation of a standard obligation under subdivision 2a, 2f, or 2g, in whole or in
1.12part, if the commission determines that modifying or delaying the standard obligation is in
1.13the public interest. The commission, when evaluating a request to modify or delay
1.14implementation of a standard, must consider:
1.15(1) the impact of implementing the standard on its customers' utility costs, including the
1.16economic and competitive pressure on the utility's customers;
1.17(2) the environmental costs that would be incurred as a result of a delay or modification,
1.18based on the full range of environmental cost values established in section 216B.2422,
1.19subdivision 3;
1.20(3) the effects of implementing the standard on the reliability of the electric system;
1.21(4) technical advances or technical concerns;
1.22(5) delays in acquiring sites or routes due to rejection or delays of necessary siting or
1.23other permitting approvals;
2.1(6) delays, cancellations, or nondelivery of necessary equipment for construction or
2.2commercial operation of an eligible energy technology facility;
2.3(7) transmission constraints preventing delivery of service;
2.4(8) other statutory obligations imposed on the commission or a utility;
2.5(9) impacts on environmental justice areas; and
2.6(10) additional electric load from beneficial electrification and the greenhouse gas
2.7emissions savings associated with those loads as compared to serving the load with
2.8nonelectric energy sources.
2.9For the purposes of this paragraph, "beneficial electrification" means the substitution of
2.10electricity for a fossil fuel, provided that the substitution meets at least one of the following
2.11conditions without adversely affecting either of the other two, as determined by the
2.12commission:
2.13(i) saves a consumer money over the long run compared with continued use of the fossil
2.14fuel;
2.15(ii) enables an electric utility to better manage the electric utility's electric grid network;
2.16or
2.17(iii) reduces negative environmental impacts of fuel use, including but not limited to
2.18statewide greenhouse gas emissions.
2.19(b) The commission may modify or delay implementation of a standard obligation under
2.20paragraph (a), clauses (1) to (4), only if it finds implementation would cause significant rate
2.21impact, requires significant measures to address reliability, or raises significant technical
2.22issues. The commission may modify or delay implementation of a standard obligation under
2.23paragraph (a), clauses (5) to (7), only if it finds that the circumstances described in those
2.24clauses were due to circumstances beyond an electric utility's control and make compliance
2.25not feasible.
2.26(c) When evaluating transmission capacity constraints under paragraph (a), clause (7),
2.27the commission must consider whether the utility has:
2.28(1) taken reasonable measures that are under the utility's control and consistent with the
2.29utility's obligations under local, state, and federal laws and regulations, and the utility's
2.30obligations as a member of a regional transmission organization or independent system
2.31operator, to acquire sites, necessary permit approvals, and necessary equipment to develop
3.1and construct new transmission lines or upgrade existing transmission lines to transmit
3.2electricity generated by eligible energy technologies; and
3.3(2) taken all reasonable operational measures to maximize cost-effective electricity
3.4delivery from eligible energy technologies in advance of transmission availability.
3.5(d) When considering whether to delay or modify implementation of a standard obligation,
3.6the commission must give due consideration to a preference for electric generation through
3.7use of eligible energy technology and to the achievement of the standards set by this section.
3.8(e) An electric utility that requests a modification or delay to the implementation of a
3.9standard must file a plan to comply with the electric utility's standard obligation as part of
3.10the same proceeding in which the electric utility requests the modification or delay.
3.11 new text begin (f) The requirement to meet a standard obligation under this section is automatically new text end
3.12 new text begin delayed for three years for an electric utility that does not meet the goal established under new text end
3.13 new text begin section 216C.05, subdivision 2, clause (4), as determined by the commissioner. new text end
3.14 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.15Sec. 2. new text begin [216B.2442] RETIRED FOSSIL-FUEL-POWERED ELECTRIC new text end
3.16 new text begin GENERATING PLANT; DEMOLITION. new text end
3.17 new text begin A political subdivision is prohibited from issuing a permit to an electric utility to demolish new text end
3.18 new text begin a fossil-fuel-powered electric generating plant if the utility fails to meet the goal established new text end
3.19 new text begin under section 216C.05, subdivision 2, clause (4), as determined by the commissioner. new text end
3.20 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.
Progress through the legislative process
In Committee