HF2928
Preapplication filings for large water appropriation projects required, permit application information for large water appropriation projects added, level of environmental review for data centers specified, data centers exempted from making financial contributions to an energy conservation and optimization plan, and other data center provisions modified.
Legislative Session 94 (2025-2026)
Related bill: SF3968
Bill text
(underlined = new law, struck through = current law the bill removes)
Versions
1.1A bill for an act
1.2relating to energy; requiring preapplication filings for large water appropriation
1.3projects; adding information to permit applications for large water appropriation
1.4projects; specifying the level of environmental review for data centers; removing
1.5data centers' energy consumption from the calculation of a utility's energy savings
1.6goal; exempting data centers from making financial contributions to an energy
1.7conservation and optimization plan; depositing fee revenues in an account to be
1.8used for energy conservation; modifying the definition of large energy facility;
1.9establishing energy requirements for data centers; imposing a fee on data centers;
1.10requiring the Public Utilities Commission to establish a new tariff for data centers;
1.11amending Minnesota Statutes 2024, sections 103G.265, by adding a subdivision;
1.12103G.271, by adding a subdivision; 116D.04, by adding a subdivision; 216B.2402,
1.13subdivision 10; 216B.241, subdivisions 1a, 2a; 216B.2421, subdivision 2; proposing
1.14coding for new law in Minnesota Statutes, chapter 216B.
1.15BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.16Section 1. Minnesota Statutes 2024, section 103G.265, is amended by adding a subdivision
1.17to read:
1.18 new text begin Subd. 5. Preapplication evaluation of large water appropriation projects. (a) This new text end
1.19 new text begin subdivision applies to a project whose proposed consumptive use exceeds 100 million new text end
1.20 new text begin gallons per year or 250,000 gallons per day, whether under an existing permit, as the result new text end
1.21 new text begin of a permit amendment, or under a new individual permit. new text end
1.22 new text begin (b) To ensure that a project is compatible with the needs of other current and future new text end
1.23 new text begin water users, to help maintain the water allocation priorities established under section new text end
1.24 new text begin 103G.261, to ensure adequate water supply in areas of the state with limited water new text end
1.25 new text begin availability, and to promote a more efficient and timely permitting process, potential new text end
1.26 new text begin applicants or persons working on behalf of potential applicants are encouraged to discuss new text end
1.27 new text begin the project with the department as early in the project development process as possible, new text end
2.1 new text begin preferably before a final project site has been selected, project design has been finalized, new text end
2.2 new text begin or land has been acquired. new text end
2.3 new text begin (c) A city or county employee that has been contacted by a person regarding a project new text end
2.4 new text begin that is likely to be subject to this subdivision must, even if no final decision has been made new text end
2.5 new text begin on the project's location, notify the department in writing within ten business days of the new text end
2.6 new text begin contact, providing the name of and contact information for the person, and potential project new text end
2.7 new text begin locations. new text end
2.8 new text begin (d) In response to a contact from a potential applicant, the department may request new text end
2.9 new text begin preapplication information that is helpful in assisting the department to assess the factors new text end
2.10 new text begin affecting the ability of a water source to meet a project's water use needs at proposed new text end
2.11 new text begin locations, including: new text end
2.12 new text begin (1) a project description, including all potential locations; new text end
2.13 new text begin (2) the project's estimated maximum daily, seasonal, and annual water use rates and new text end
2.14 new text begin volumes; new text end
2.15 new text begin (3) the anticipated source of water; and new text end
2.16 new text begin (4) water quality or temperature requirements. new text end
2.17 new text begin The department may request any additional information necessary to assist it to assess the new text end
2.18 new text begin ability of a water source to meet a project's water use needs. new text end
2.19 new text begin (e) The commissioner shall evaluate the information supplied by a potential applicant new text end
2.20 new text begin under this subdivision and shall respond in writing, which may be electronically transmitted, new text end
2.21 new text begin describing potential water availability constraints at each proposed project site. new text end
2.22 new text begin (f) In determining the impact of a potential project on water quality and quantity, the new text end
2.23 new text begin commissioner may consult with the commissioners of health, agriculture, the Pollution new text end
2.24 new text begin Control Agency, and other state agencies. new text end
2.25 new text begin (g) Any communication made or information exchanged under this subdivision between new text end
2.26 new text begin a potential applicant and a government agency, or between government agencies, is nonpublic new text end
2.27 new text begin data, as defined in section 13.02, until the project is either abandoned or the applicant files new text end
2.28 new text begin an application for a water use permit under section 103G.285 or 103G.287, after which the new text end
2.29 new text begin data is public. new text end
2.30 new text begin (h) None of the discussions, filings, or evaluations made under this subdivision preclude new text end
2.31 new text begin or supplant environmental review, preliminary well-construction approval, appropriation new text end
2.32 new text begin permit review, or any other requirements under federal, state, or local law. new text end
3.1 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.2Sec. 2. Minnesota Statutes 2024, section 103G.271, is amended by adding a subdivision
3.3to read:
3.4 new text begin Subd. 5b. Large water appropriation projects; permit conditions. In issuing water new text end
3.5 new text begin use permits to applicants that meet the criteria of section 103G.265, subdivision 5, the new text end
3.6 new text begin department shall ensure that: new text end
3.7 new text begin (1) water resources of the state are utilized in the public interest and that public health, new text end
3.8 new text begin safety, and welfare are adequately protected; new text end
3.9 new text begin (2) technologies that promote water conservation and the efficient use of water are fully new text end
3.10 new text begin considered; and new text end
3.11 new text begin (3) water use conflicts are addressed as prescribed in Minnesota Rules, part 6115.0740. new text end
3.12 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.13Sec. 3. Minnesota Statutes 2024, section 116D.04, is amended by adding a subdivision to
3.14read:
3.15 new text begin Subd. 18. Data centers; environmental review. (a) Notwithstanding any law to the new text end
3.16 new text begin contrary, the proposed construction of a data center, as defined in section 216B.71, or the new text end
3.17 new text begin expansion of the average hourly load of an existing data center by 100 megawatts or more, new text end
3.18 new text begin requires preparation of an environmental impact statement according to the provisions of new text end
3.19 new text begin subdivision 2a. The responsible governmental unit for the environmental impact statement new text end
3.20 new text begin is the Public Utilities Commission. new text end
3.21 new text begin (b) For the purposes of this subdivision, "average hourly load" means the amount of new text end
3.22 new text begin electricity consumed by a facility each hour, averaged over an entire year. new text end
3.23 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
3.24Sec. 4. Minnesota Statutes 2024, section 216B.2402, subdivision 10, is amended to read:
3.25Subd. 10. Gross annual retail energy sales. "Gross annual retail energy sales" means
3.26a utility's annual electric sales to all Minnesota retail customers, or natural gas throughput
3.27to all retail customers, including natural gas transportation customers, on a utility's
3.28distribution system in Minnesota. Gross annual retail energy sales does not include:
3.29(1) gas sales to:
3.30(i) a large energy facility;
4.1(ii) a large customer facility whose natural gas utility has been exempted by the
4.2commissioner under section 216B.241, subdivision 1a, paragraph (a), with respect to natural
4.3gas sales made to the large customer facility; and
4.4(iii) a commercial gas customer facility whose natural gas utility has been exempted by
4.5the commissioner under section 216B.241, subdivision 1a, paragraph (b), with respect to
4.6natural gas sales made to the commercial gas customer facility;
4.7(2) electric sales to:
4.8(i) a large customer facility whose electric utility has been exempted by the commissioner
4.9under section 216B.241, subdivision 1a, paragraph (a), with respect to electric sales made
4.10to the large customer facility; deleted text begin and deleted text end
4.11(ii) a data mining facility, if the facility:
4.12(A) has provided a signed letter to the utility verifying the facility meets the definition
4.13of a data mining facility; and
4.14(B) imposes a peak electrical demand on a consumer-owned utility's system equal to or
4.15greater than 40 percent of the peak electrical demand of the system, measured in the same
4.16manner as the utility that serves the customer facility measures electric demand for billing
4.17purposes; deleted text begin or deleted text end new text begin and new text end
4.18 new text begin (iii) a data center, as defined in section 216B.71; or new text end
4.19(3) the amount of electric sales prior to December 31, 2032, that are associated with a
4.20utility's program, rate, or tariff for electric vehicle charging based on a methodology and
4.21assumptions developed by the department in consultation with interested stakeholders no
4.22later than December 31, 2021. After December 31, 2032, incremental sales to electric
4.23vehicles must be included in calculating a public utility's gross annual retail sales.
4.24 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
4.25Sec. 5. Minnesota Statutes 2024, section 216B.241, subdivision 1a, is amended to read:
4.26Subd. 1a. Large customer facility. (a) The owner of a large customer facility may
4.27petition the commissioner to exempt both electric and gas utilities serving the large customer
4.28facility from contributing to investments and expenditures made under an energy and
4.29conservation optimization plan filed under subdivision 2 or section 216B.2403, subdivision
4.303, with respect to retail revenues attributable to the large customer facility. The filing must
4.31include a discussion of the competitive or economic pressures facing the owner of the facility
4.32and the efforts taken by the owner to identify, evaluate, and implement energy conservation
5.1and efficiency improvements. A filing submitted on or before October 1 of any year must
5.2be approved within 90 days and become effective January 1 of the year following the filing,
5.3unless the commissioner finds that the owner of the large customer facility has failed to
5.4take reasonable measures to identify, evaluate, and implement energy conservation and
5.5efficiency improvements. If a facility qualifies as a large customer facility solely due to its
5.6peak electrical demand or annual natural gas usage, the exemption may be limited to the
5.7qualifying utility if the commissioner finds that the owner of the large customer facility has
5.8failed to take reasonable measures to identify, evaluate, and implement energy conservation
5.9and efficiency improvements with respect to the nonqualifying utility. Once an exemption
5.10is approved, the commissioner may request the owner of a large customer facility to submit,
5.11not more often than once every five years, a report demonstrating the large customer facility's
5.12ongoing commitment to energy conservation and efficiency improvement after the exemption
5.13filing. The commissioner may request such reports for up to ten years after the effective
5.14date of the exemption, unless the majority ownership of the large customer facility changes,
5.15in which case the commissioner may request additional reports for up to ten years after the
5.16change in ownership occurs. The commissioner may, within 180 days of receiving a report
5.17submitted under this paragraph, rescind any exemption granted under this paragraph upon
5.18a determination that the large customer facility is not continuing to make reasonable efforts
5.19to identify, evaluate, and implement energy conservation improvements. A large customer
5.20facility that is, under an order from the commissioner, exempt from the investment and
5.21expenditure requirements of paragraph (a) as of December 31, 2010, is not required to
5.22submit a report to retain its exempt status, except as otherwise provided in this paragraph
5.23with respect to ownership changes. No exempt large customer facility may participate in a
5.24utility conservation improvement program unless the owner of the facility submits a filing
5.25with the commissioner to withdraw its exemption. new text begin A data center that pays the required fee new text end
5.26 new text begin under section 216B.72 is exempt from the requirement to contribute to investments and new text end
5.27 new text begin expenditures made under an energy conservation optimization plan filed under subdivision new text end
5.28 new text begin 2 or section 216B.2403, subdivision 3, and is not required to comply with the provisions new text end
5.29 new text begin of this paragraph. new text end
5.30(b) A commercial gas customer that is not a large customer facility and that purchases
5.31or acquires natural gas from a public utility having fewer than 600,000 natural gas customers
5.32in Minnesota may petition the commissioner to exempt gas utilities serving the commercial
5.33gas customer from contributing to investments and expenditures made under an energy and
5.34conservation optimization plan filed under subdivision 2 or section 216B.2403, subdivision
5.353, with respect to retail revenues attributable to the commercial gas customer. The petition
5.36must be supported by evidence demonstrating that the commercial gas customer has acquired
6.1or can reasonably acquire the capability to bypass use of the utility's gas distribution system
6.2by obtaining natural gas directly from a supplier not regulated by the commission. The
6.3commissioner shall grant the exemption if the commissioner finds that the petitioner has
6.4made the demonstration required by this paragraph.
6.5(c) A public utility, consumer-owned utility, or owner of a large customer facility may
6.6appeal a decision of the commissioner under paragraph (a) or (b) to the commission under
6.7subdivision 2. In reviewing a decision of the commissioner under paragraph (a) or (b), the
6.8commission shall rescind the decision if it finds the decision is not in the public interest.
6.9(d) Notwithstanding paragraph (a), a large customer facility or commercial gas customer
6.10that is exempt from the investment and expenditure requirements of this section pursuant
6.11to an order from the commissioner as of December 31, 2020, is not required to submit
6.12additional documentation to maintain the exemption and must not be assessed any costs
6.13related to any energy conservation and optimization plan filed under this section or section
6.14216B.2403, including but not limited to costs, incentives, or rates of return associated with
6.15investments in programs for efficient fuel-switching improvements.
6.16(e) A public utility is prohibited from spending for or investing in energy conservation
6.17improvements that directly benefit a large energy facility or a large electric customer facility
6.18the commissioner has issued an exemption to under this section.
6.19 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
6.20Sec. 6. Minnesota Statutes 2024, section 216B.241, subdivision 2a, is amended to read:
6.21Subd. 2a. Energy and conservation account. new text begin (a) new text end The energy and conservation account
6.22is established in the special revenue fund in the state treasury.
6.23 new text begin (b) new text end The commissioner must deposit money assessed or contributed under subdivisions
6.241d, 1e, 1f, and 7 in the state treasury and credit it to the energy and conservation account
6.25in the special revenue fund. Money in the account new text begin assessed or contributed under subdivisions new text end
6.26 new text begin 1d, 1e, and 1f new text end is appropriated to the commissioner for the purposes of subdivisions 1d, 1e,
6.271f, and 7.
6.28 new text begin (c) The commissioner must deposit money transferred from the fee on data centers new text end
6.29 new text begin established in section 216B.72 in the state treasury and credit it to the account. Money new text end
6.30 new text begin transferred from the fee on data centers is appropriated to the commissioner to conduct new text end
6.31 new text begin energy conservation, weatherization, and associated activities allowed under sections new text end
6.32 new text begin 216B.2403 and 216B.241, and the rules applicable to those sections. The commissioner new text end
6.33 new text begin may spend money appropriated under this paragraph anywhere in the state, but only: new text end
7.1 new text begin (1) on low-income programs; and new text end
7.2 new text begin (2) as the result of a request for proposals process administered by the department. new text end
7.3 new text begin (d) new text end Interest on money in the account accrues to the account.
7.4 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
7.5Sec. 7. Minnesota Statutes 2024, section 216B.2421, subdivision 2, is amended to read:
7.6Subd. 2. Large energy facility. "Large energy facility" means:
7.7(1) any electric power generating plant or combination of plants at a single site with a
7.8combined capacity of 50,000 kilowatts or more and transmission lines directly associated
7.9with the plant that are necessary to interconnect the plant to the transmission system new text begin . Large new text end
7.10 new text begin energy facility includes backup generators designed to provide electricity to a data center, new text end
7.11 new text begin as defined in section 216B.71, with a combined capacity of 50,000 kilowatts or more new text end ;
7.12(2) any high-voltage transmission line with a capacity of 300 kilovolts or more and
7.13greater than one mile in length in Minnesota;
7.14(3) any high-voltage transmission line with a capacity of 100 kilovolts or more with
7.15more than ten miles of its length in Minnesota;
7.16(4) any pipeline greater than six inches in diameter and having more than 50 miles of
7.17its length in Minnesota used for the transportation of coal, crude petroleum or petroleum
7.18fuels or oil, or their derivatives;
7.19(5) any pipeline for transporting natural or synthetic gas at pressures in excess of 200
7.20pounds per square inch with more than 50 miles of its length in Minnesota;
7.21(6) any facility designed for or capable of storing on a single site more than 100,000
7.22gallons of liquefied natural gas or synthetic gas;
7.23(7) any underground gas storage facility requiring a permit pursuant to section 103I.681;
7.24(8) any nuclear fuel processing or nuclear waste storage or disposal facility; and
7.25(9) any facility intended to convert any material into any other combustible fuel and
7.26having the capacity to process in excess of 75 tons of the material per hour.
7.27 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
8.1Sec. 8. new text begin [216B.71] DATA CENTERS; ENERGY REQUIREMENTS. new text end
8.2 new text begin Subdivision 1. Definitions. (a) For purposes of this section, the following terms have new text end
8.3 new text begin the meanings given. new text end
8.4 new text begin (b) "Carbon-free" has the meaning given in section 216B.1691, subdivision 1. new text end
8.5 new text begin (c) "Data center" means a facility whose primary purpose is the storage, management, new text end
8.6 new text begin and processing of digital data via the interconnection and operation of information technology new text end
8.7 new text begin and network telecommunications equipment, including all related facilities and infrastructure new text end
8.8 new text begin for power distribution, environmental control, cooling, and security, and whose average new text end
8.9 new text begin hourly electrical load is 100 megawatts or greater. new text end
8.10 new text begin (d) "Political subdivision" means a county, statutory or home rule charter city, town, the new text end
8.11 new text begin Metropolitan Council, a port authority, economic development authority, redevelopment new text end
8.12 new text begin agency established under chapter 469, or regional development commission. new text end
8.13 new text begin Subd. 2. Carbon-free energy. (a) A data center must, prior to December 31, 2030, new text end
8.14 new text begin arrange to generate or procure carbon-free energy equal to at least 65 percent of its electricity new text end
8.15 new text begin consumption, measured on an hourly basis. new text end
8.16 new text begin (b) After December 31, 2030, a data center must generate or purchase carbon-free energy new text end
8.17 new text begin equal to 100 percent of its electricity requirements, measured on an hourly basis. new text end
8.18 new text begin (c) Tracking and verification of compliance with this subdivision shall be determined new text end
8.19 new text begin by the Minnesota Renewable Energy Tracking System or another qualified entity approved new text end
8.20 new text begin by the commission. new text end
8.21 new text begin (d) Each data center shall, before beginning operations in this state, submit a plan to the new text end
8.22 new text begin commission describing the actions it intends to take to comply with the requirement of new text end
8.23 new text begin paragraph (b), and shall make additional filings as required by the commission. new text end
8.24 new text begin (e) The commission may delay or modify a data center's compliance with the requirements new text end
8.25 new text begin of paragraph (a) or (b) if it determines that technical constraints impair the ability to new text end
8.26 new text begin accurately track and verify carbon-free energy transactions at an hourly level so as to enable new text end
8.27 new text begin compliance with those requirements. new text end
8.28 new text begin Subd. 3. State energy targets; modification. If a utility determines that providing new text end
8.29 new text begin electric service to a data center may, in whole or in part, contribute to the utility's inability new text end
8.30 new text begin to achieve a standard mandated under section 216B.1691, the utility must, no later than two new text end
8.31 new text begin years before the standard is required to be met, submit a filing to the commission containing new text end
8.32 new text begin a plan describing actions the utility intends to implement in order to achieve the standard new text end
8.33 new text begin in a timely manner. The commission shall review and may accept, reject, or modify the plan new text end
9.1 new text begin and may issue an order requiring implementation of an approved plan. The commission new text end
9.2 new text begin shall require a utility whose plan was approved under this subdivision to file reports with new text end
9.3 new text begin the commission describing actions taken and progress made in achieving the standard, on new text end
9.4 new text begin a schedule determined by the commission. new text end
9.5 new text begin Subd. 4. Prevailing wage. A contractor or subcontractor that constructs any portion of new text end
9.6 new text begin a data center: new text end
9.7 new text begin (1) must pay no less than the prevailing wage rate, as defined in section 177.42; and new text end
9.8 new text begin (2) is subject to the requirements and enforcement provisions under sections 177.27, new text end
9.9 new text begin 177.30, 177.32, 177.41 to 177.435, and 177.45. new text end
9.10 new text begin Subd. 5. Reporting. (a) Within one year of being placed in service, and annually new text end
9.11 new text begin thereafter on a schedule determined by the commissioner, a data center owner must report new text end
9.12 new text begin the following information to the commissioner on a form and on a schedule prescribed by new text end
9.13 new text begin the commissioner of commerce: new text end
9.14 new text begin (1) energy consumption during the most recently completed year and during each of the new text end
9.15 new text begin past five years, if applicable, and projections of energy consumption for the coming year; new text end
9.16 new text begin (2) efforts made to reduce energy consumption; new text end
9.17 new text begin (3) efforts made to reduce waste heat and to utilize it as thermal energy or electricity; new text end
9.18 new text begin and new text end
9.19 new text begin (4) the amount, type, and country of origin of metals used to construct the data center, new text end
9.20 new text begin and the percentage of metals used that were recycled. new text end
9.21 new text begin (b) Within one year of being placed in service, and annually thereafter on a schedule new text end
9.22 new text begin determined by the commissioner of natural resources, a data center owner must report the new text end
9.23 new text begin following information to the commissioner of natural resources, on a form and on a schedule new text end
9.24 new text begin prescribed by the commissioner of natural resources: new text end
9.25 new text begin (1) the amount of water withdrawn under the data center's water use permit; new text end
9.26 new text begin (2) the amount of water discharged by the data center to groundwater or surface waters; new text end
9.27 new text begin and new text end
9.28 new text begin (3) the amount of water evaporated when used for cooling data center equipment. new text end
9.29 new text begin Subd. 6. Noncompliance; ineligibility for financial assistance. Notwithstanding any new text end
9.30 new text begin other law, a data center that fails to comply with any of the requirements of this section is new text end
9.31 new text begin ineligible to receive any financial incentives provided by this state for which it is otherwise new text end
9.32 new text begin eligible, including tax incentives, until it has submitted documentation of compliance to the new text end
10.1 new text begin commissioner of commerce and has received written notice from the commissioner of new text end
10.2 new text begin commerce that it is in compliance with all the provisions of this section. new text end
10.3 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
10.4Sec. 9. new text begin [216B.72] DATA CENTER FEE. new text end
10.5 new text begin (a) A fee of $....... is imposed on a data center, as defined in section 216B.71, for each new text end
10.6 new text begin megawatt of the data center's peak demand. The fee must be collected monthly by the utility new text end
10.7 new text begin providing electric service to the data center and deposited in the energy and conservation new text end
10.8 new text begin account established in section 216B.241, subdivision 2a. new text end
10.9 new text begin (b) For the purposes of this section, "peak demand" means the largest demand a data new text end
10.10 new text begin center imposes on an electric utility's system, expressed in megawatts, during a 30-minute new text end
10.11 new text begin period within the most recent month. new text end
10.12 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
10.13Sec. 10. new text begin CLEAN ENERGY TARIFF. new text end
10.14 new text begin (a) No later than January 1, 2026, the Public Utilities Commission shall develop and new text end
10.15 new text begin establish a clean energy tariff and terms and conditions for energy supply agreements under new text end
10.16 new text begin which a separate customer class composed solely of all data centers receiving electric service new text end
10.17 new text begin from a public utility located in this state must operate. The tariff and energy supply agreement new text end
10.18 new text begin must be designed to insulate the utility's other customers from the energy costs attributable new text end
10.19 new text begin to data centers and to ensure that arrangements made to provide electric service to a data new text end
10.20 new text begin center will: new text end
10.21 new text begin (1) not interfere with or jeopardize a utility's achieving the mandated renewable energy new text end
10.22 new text begin and carbon-free standards established under Minnesota Statutes, sections 216B.1691 and new text end
10.23 new text begin 216B.71, subdivision 2; new text end
10.24 new text begin (2) not impair a utility's system reliability or its ability to provide electric service to its new text end
10.25 new text begin other customers; new text end
10.26 new text begin (3) require payment of the data center's full portion of the utility's cost to procure new text end
10.27 new text begin electricity, and for the full transmission and distribution costs necessary to deliver that new text end
10.28 new text begin electricity to the data center, including any construction or upgrading of transmission, new text end
10.29 new text begin distribution, or other utility infrastructure; and new text end
10.30 new text begin (4) ensure that ratepayers are fully protected from bearing any portion of the cost resulting new text end
10.31 new text begin from: new text end
11.1 new text begin (i) a data center's failure to meet its projected level of electricity demand; new text end
11.2 new text begin (ii) a data center's termination of its operations in this state earlier than agreed to in an new text end
11.3 new text begin energy supply agreement; new text end
11.4 new text begin (iii) an electricity supplier's failure to fully meet the terms of its supply contract with new text end
11.5 new text begin the utility; or new text end
11.6 new text begin (iv) early termination of an energy supply agreement. new text end
11.7 new text begin (b) The Public Utilities Commission may require a data center to post a bond of sufficient new text end
11.8 new text begin magnitude to guarantee performance under the tariff and energy supply agreement. new text end
11.9 new text begin (c) For purposes of this section, the following terms have the meanings given: new text end
11.10 new text begin (1) "data center" has the meaning given in Minnesota Statutes, section 216B.71, new text end
11.11 new text begin subdivision 1; and new text end
11.12 new text begin (2) "energy supply agreement" means an agreement between a data center and a utility new text end
11.13 new text begin providing electric service to a data center governing the transfer of electricity from a generator new text end
11.14 new text begin to the data center under a clean energy tariff. new text end
11.15 new text begin EFFECTIVE DATE. This section is effective the day following final enactment. new text end
Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.