1.1A bill for an act
1.2relating to transit; requiring a cost-benefit analysis for proposed guideways;
1.3requiring a report; proposing coding for new law in Minnesota Statutes, chapter
1.4473.
1.5BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF MINNESOTA:
1.6Section 1. new text begin [473.4487] GUIDEWAY COST-BENEFIT ANALYSIS. new text end
1.7 new text begin Subdivision 1. Definitions. (a) For purposes of this section, the following terms have new text end
1.8 new text begin the meanings given. new text end
1.9 new text begin (b) "Commissioner" means the commissioner of transportation. new text end
1.10 new text begin (c) "Project options" means the proposed guideway and each alternative identified new text end
1.11 new text begin pursuant to subdivision 2, paragraph (b). new text end
1.12 new text begin (d) "Responsible governmental unit" means the unit of government responsible for the new text end
1.13 new text begin environmental analysis of the project. new text end
1.14 new text begin Subd. 2. Analysis required. (a) Prior to the selection of a locally preferred alternative, new text end
1.15 new text begin the responsible governmental unit must perform a cost-benefit analysis as described by this new text end
1.16 new text begin section. The responsible governmental unit must submit the analysis to the commissioner new text end
1.17 new text begin and the Metropolitan Council within 30 days of completing the analysis. The commissioner new text end
1.18 new text begin must post the final analysis on the Department of Transportation's website. The chair of the new text end
1.19 new text begin Metropolitan Council must post the final analysis on the council's website. The commissioner new text end
1.20 new text begin and the council must jointly submit a copy of the final report to the legislative auditor and new text end
1.21 new text begin to the chairs and ranking minority members of the legislative committees with jurisdiction new text end
1.22 new text begin over transportation finance and policy. new text end
2.1 new text begin (b) The responsible governmental unit must determine alternatives that would serve new text end
2.2 new text begin substantially the same area as the proposed guideway but would provide service in a different new text end
2.3 new text begin manner. At a minimum, the alternatives must include an arterial bus rapid transit line, a new text end
2.4 new text begin regular route bus service line, and a nontransit option that expands capacity of the road. new text end
2.5 new text begin (c) At a minimum, the analysis must include the following information: new text end
2.6 new text begin (1) for guideway and busway project options, the estimated ridership numbers; new text end
2.7 new text begin (2) for the capacity expansion option, the number of additional vehicles accommodated new text end
2.8 new text begin by the expansion; new text end
2.9 new text begin (3) for each project option, an estimate of the increase or decrease of the number of new text end
2.10 new text begin vehicles on the road; new text end
2.11 new text begin (4) the amount of revenue derived from or attributable to each project option, including new text end
2.12 new text begin but not limited to fares, tax on gasoline, and motor vehicle sales tax; new text end
2.13 new text begin (5) for each project option, the estimated ongoing maintenance costs, which entity will new text end
2.14 new text begin pay for the costs, and the percentage of the costs to be paid by each entity; new text end
2.15 new text begin (6) for each project option, the estimated future capital costs, which entity will pay for new text end
2.16 new text begin the costs, and the percentage of the costs to be paid by each entity; new text end
2.17 new text begin (7) the estimated economic benefit attributable to each project option, including but not new text end
2.18 new text begin limited to new or expanded housing units or businesses, increased freight movement, and new text end
2.19 new text begin reduction of supply chain issues; new text end
2.20 new text begin (8) for each project option, the estimated timeline for construction, road closures, and new text end
2.21 new text begin detours and an estimate on how that timeline affects the surrounding areas; new text end
2.22 new text begin (9) for each project option, an estimate of whether vehicle collisions will increase or new text end
2.23 new text begin decrease due to a change in the projected number of vehicles on the road; new text end
2.24 new text begin (10) for each project option, an analysis of whether each project option could be altered new text end
2.25 new text begin or stopped once construction is started and the estimated costs related to alteration or new text end
2.26 new text begin stopping; new text end
2.27 new text begin (11) for each project option, travel time along the route from end to end and for various new text end
2.28 new text begin points of interest in between, including time spent waiting for transit, changing modes of new text end
2.29 new text begin transportation, and other time spent directly related to travel but not inside of a vehicle; new text end
2.30 new text begin (12) for busway and guideway project options, how travel time for vehicles would be new text end
2.31 new text begin affected by any estimated reduction in vehicle traffic; and new text end
3.1 new text begin (13) for each project option, the estimated increase or decrease in carbon emissions or new text end
3.2 new text begin other environmental pollutants. new text end
3.3 new text begin (d) The analysis must also determine how many miles of arterial bus rapid transit, regular new text end
3.4 new text begin route bus service, or congestion mitigation construction could be funded for the amount new text end
3.5 new text begin proposed to be spent on the guideway. new text end
3.6 new text begin (e) A responsible governmental unit may request assistance from the commissioner or new text end
3.7 new text begin the Metropolitan Council. The commissioner or the Metropolitan Council must provide the new text end
3.8 new text begin requested assistance and may bill the responsible governmental unit for reasonable expenses new text end
3.9 new text begin incurred in providing the assistance. new text end
3.10 new text begin EFFECTIVE DATE; APPLICATION. This section is effective the day following new text end
3.11 new text begin final enactment and applies to all guideways seeking state or federal funding on or after new text end
3.12 new text begin that date, except this section does not apply to the Gold Line bus rapid transit project. This new text end
3.13 new text begin section applies in the counties of Anoka, Carver, Dakota, Hennepin, Ramsey, Scott, and new text end
3.14 new text begin Washington. new text end
3.15Sec. 2. new text begin GUIDEWAY COST-BENEFIT ANALYSIS; TRANSITION. new text end
3.16 new text begin (a) This section applies to a guideway for which a locally preferred alternative has been new text end
3.17 new text begin selected prior to the effective date of this section but is not in revenue operation on the new text end
3.18 new text begin effective date of this section, except this section does not apply to the Gold Line bus rapid new text end
3.19 new text begin transit project. new text end
3.20 new text begin (b) For each guideway subject to this section, the commissioner of transportation and new text end
3.21 new text begin the Metropolitan Council must perform a cost-benefit analysis as required by Minnesota new text end
3.22 new text begin Statutes, section 473.4487, subdivision 2, paragraphs (b), (c), and (d). Within 30 days of new text end
3.23 new text begin completing a cost-benefit analysis required by this section, the commissioner must post the new text end
3.24 new text begin final analysis on the Department of Transportation's website and the Metropolitan Council new text end
3.25 new text begin must post the final analysis on the council's website. The commissioner and the council new text end
3.26 new text begin must jointly submit a copy of the final report to the legislative auditor and to the chairs and new text end
3.27 new text begin ranking minority members of legislative committees with jurisdiction over transportation new text end
3.28 new text begin finance and policy. new text end
3.29 new text begin EFFECTIVE DATE; APPLICATION. This section is effective the day following new text end
3.30 new text begin final enactment and applies in the counties of Anoka, Carver, Dakota, Hennepin, Ramsey, new text end
3.31 new text begin Scott, and Washington. new text end

Bill information comes from public records published by the Office of the Revisor of Statutes, the Minnesota House and the Minnesota Senate. AI summaries are written by MinneSlate and are not official. MinneSlate is independent and is not affiliated with the State of Minnesota or the Minnesota Legislature.

Progress through the legislative process

17%
In Committee
Loading…